Matter of Red Hook 160 LLC v. Borough Constr. Grp. LLC, No. 524909/18, 2019 BL 122210 (N.Y. Sup. Ct. Mar. 19, 2019)
This cases arises out of a project owner’s request for further itemization of amounts claimed in a construction manager’s mechanic’s lien. Red Hook 160 LLC (“Red Hook”), the owner of the property sought to be liened, demanded a revised itemized statement of the mechanics’ lien filed by Borough Construction Group, LLC (“BCG”), the construction manager hired in connection with the construction and renovation of a six story building located at 160 Imlay Street in Kings County, New York.
Florida Federal Court Dismisses Fluor Enterprises’ $67M Claim Against Duke Energy for Wrongful Draw Down of Credit Letter
Tampa D Fluor Enterprises, Inc. v. Duke Energy Florida, LLC, No. 8:19-cv-00224, 2019 BL 135007, at *1 (M.D. Fla. Apr. 16, 2019)
On April 16, 2019, a Florida federal court dismissed without prejudice Fluor Enterprises’ claim that Duke Energy wrongfully drew down a $67 million letter of credit issued in connection with Fluor’s construction of a gas-fired electrical generation facility in Citrus County, Florida. In addition to the core breach of contract claim which suffered from several procedural issues, the court dismissed extra-contractual claims for conversion, civil theft, breach of the implied covenant of good faith and fair dealing, and violation of the Florida Deceptive and Unfair Trade Practices Act.
Court of Federal Claim Rejects Spearin Claim and Holds Contractor Responsible for Failure to Prevent Mold Growth
James Talcott Construction, Inc. v. United States, No. 14-427 C, 2019 BL 72711, at *1 (Fed. Cl. Mar. 4, 2019)
In May of 2010, the United States, acting through the Department of Defense (the “Government”) awarded a contract to James Talcott Construction, Inc. (“Talcott”) to replace existing housing for military families at the Malmstrom Air Force Base in Great Falls, Montana. Talcott was required to construct thirteen buildings, each comprising seventy housing units. Each building was to be constructed with concrete foundations and wood framing, and the project’ design called for wooden floor joists and subfloor decking to be enclosed in crawlspaces. The contract stated that the “structural drawings and specification represent the finished structure… [but] do not indicate the method of construction. The contractor will provide all measures necessary to protect the structure during construction.” The plans and specifications were silent as to ventilation of the crawlspaces.
District Court in Wisconsin Finds That Counteroffer and Repeated Negotiations Concerning a Construction Contract Do Not Create Contractual Relationship
Skyrise Construction Group, LLC v. Annex Construction, LLC, 2019 BL 55071 (E.D. Wis. Feb. 20, 2019)
Subcontractor Skyrise Construction, Inc. (“Skyrise”) sued general contractor Annex Construction, Inc. (“Annex”) for breach of contract, promissory estoppel, negligent misrepresentation, and violations of Wisconsin and Illinois trade practices statutes. Skyrise primarily based its claims on an assertion that the parties entered into a subcontract, which Annex breached when it removed Skyrise from the project and completed the work with an alternative subcontractor. Both Skyrise and Annex filed motions for summary judgment. The District Court denied Skyrise’s motion and granted Annex’s motion.
The Washington Court of Appeals Clarifies When the Statute of Limitations for a Negligence Claim Begins to Run Under the Discovery Rule
Dep’t of Transp. v. Seattle Tunnel Partners, 2019 BL 36988, 2 (Wash. App. Div. 2 Feb. 05, 2019)
On January 8, 2019, the Court of Appeals for the State of Washington reversed and remanded in part a trial court’s grant of summary judgment in a tunnel-boring construction case. Specifically, the Court clarified that the three-year statute of limitations for negligence claims begins to run as soon as the aggrieved party becomes aware of the factual elements of the claims. It does not matter whether the underlying cause of the claims remains disputed.
A Pivotal Ruling for Appellate Arbitration Award Enforcement
This article was published in Law360 on March 11, 2019. © Copyright 2019, Portfolio Media, Inc., publisher of Law360. It is republished here with permission.
In 2008, the U.S. Supreme Court in Hall Street Associates LLC v. Mattel Inc. determined that parties may not contractually agree to expand judicial…
New York Appellate Court Holds That Affidavits Can Cure Pleading Defects and Extrinsic Evidence Permitted When Contract Clause Is Ambiguous
Servidone, Inc./B. Anthony Constr. Corp., J.V. v. State of New York, No. 2016-05238, 2019 BL 7232 (App. Div., 2d Dept. Jan. 09, 2019)
Servidone, Inc./B. Anthony Construction Corp., J.V. (the “Contractor”) and the New York State Department of Transportation (the “DOT”) entered into a construction contract to reconstruct and replace bridges on Route 59 in New York State. The Contractor retained L.M. Sessler Excavating & Wrecking, Inc. (the “Subcontractor”) to perform the demolition and disposal portion of the project.
Ninth Circuit Finds Arbitration Award Is ‘Irrational’ Because It Disregards the Contract’s Plain Text Simply to Reach a Just Result
Aspic Eng’g & Constr. Co. v. ECC Centcom Constructors LLC, No. 17-16510, 2019 BL 26363 (9th Cir. Jan. 28, 2019)
Aspic Engineering and Construction Company (“Aspic”), a local Afghan subcontractor, entered into multiple subcontracts with ECC Centcom Constructors and ECC International (“ECC”), the prime contractor, to construct buildings and facilities in Afghanistan. The subcontracts contained terms and conditions “applicable to all U.S. Government subcontracts,” and mandated that Aspic owed ECC the same obligations that ECC owed to the federal government. The subcontracts also incorporated multiple Federal Acquisition Regulation (“FAR”) clauses, including FAR 49.2 through 49.6, which govern the recovery of expenses in the event a contractor is terminated for convenience, i.e. required documentation and procedures.
Federal Court in Maryland Holds Subcontractor Waived Right to Bring Labor Inefficiency Claim Despite Voicing ‘Expression[s] of Frustration’ and ‘General Complaints’ of Mismanagement Throughout Project
Hagen Constr. Inc. v. Whiting-Turner Contracting Co., No. JKB-18-1201, 2019 BL 36862 (D. Md. Feb. 04, 2019)
This case arises out of the construction of a pediatric outpatient center in southern New Jersey. Plaintiff subcontractor Hagen Construction, Inc. (“Hagen”) filed suit in New Jersey state Court against defendant general contractor Whiting-Turner Construction Co. (“W-T”), seeking reimbursement for labor inefficiency costs incurred as a result of W-T’s alleged project mismanagement. Hagen claimed it incurred additional costs to repeat work and remobilize to multiple areas because it was not afforded unimpeded access or timely supply of necessary materials and information. Once the case was removed and transferred to Maryland federal Court, W-T moved for partial summary judgment on the portion of Hagen’s breach of contract claim reflecting labor inefficiency costs.
The Doctrine of Arbitral Immunity Applied to an Arbitral Organization Absent a Showing of Clear Lack of Jurisdiction
Univ. of Iowa Bd. of Regents v. Am. Arbitration Ass’n, No. 17-0949, 2019 BL 7069 (Iowa Ct. App. Jan. 09, 2019)
Modern Piping, Inc. (“Modern Piping”) and the University of Iowa, Board of Regents, and State of Iowa (“University”) entered into two construction contracts, both containing arbitration provisions. Disputes arose related to each contract and Modern Piping filed a demand for arbitration with the American Arbitration Association (AAA). The University filed an action against AAA, seeking to enjoin it from arbitrating the disputes. AAA filed a motion for summary judgment on the grounds that arbitral immunity doctrine applied. The district court granted AAA’s motion and the University appealed.
The doctrine of arbitral immunity provides that arbitrators are immune from liability for acts performed in their arbitral capacity and generally shields all functions which are integrally related to the arbitral process. The doctrine applies to a claim against an arbitrator where the claim effectively seeks to challenge the decisional act of an arbitrator or arbitration panel. The immunity extends to associations administering arbitration procedures.