SMJ Gen. Constr., Inc. v. Jet Commer. Constr., LLC, No. S-16785/16985, 2019 BL 131640 (Alaska Apr. 12, 2019)

In 2016, Jet Commercial Construction, LLC (“Jet”) entered into a subcontract with SMJ General Construction, Inc. (“SMJ”) to supply materials and labor for the construction of a restaurant in Hawaii.  The subcontract contained a dispute resolution provision that required the parties to first mediate any dispute and then submit it to arbitration if mediation was unsuccessful.  It also included a choice-of-law and venue provision designating Oklahoma Law and the courts of Cleveland County, Oklahoma for any lawsuits pertaining to the Agreement’s enforcement.

R&O Constr. Co. v. MBA Gen. Contracting, LLC, No. 1:18-cv-00042, 2019 BL 98680 (D. Utah Mar. 21, 2019)

On March 21, 2019, a Utah federal court granted Defendants MBA General Contracting, LLC and Cory Martin’s motion to dismiss R&O Construction Company’s claim for attorney fees.
R&O, as general contractor of a construction project, entered into two subcontracts with MBA to perform concrete work.  The first subcontract, entitled Master Subcontract Agreement, outlined general obligations between the parties.  The second, entitled Work Authorization Document, outlined more specific obligations.  R&O asserted various causes of action against MBA arising from MBA’s alleged breach of the subcontracts, including a claim for attorney fees.  MBA moved to dismiss the attorney fees claim, arguing that neither subcontract provides for such an award.

Columbia Gas Transmission, LLC v. Ohio Valley Coal Co., 2019 BL 99544 (Ohio Ct. App. Mar. 21, 2019)

Columbia Gas Transmission, LLC (“Columbia”) operated a high-pressure gas pipeline.  A portion of pipeline crossed land for which Ohio Valley Coal Company (“OVC”) and Consolidated Land Company (“Consolidated”) held interest rights in the underlying coal.  Columbia undertook measures to protect its pipeline from subsidence damage that OVC’s subterranean coal mining was certain to cause.  An Ohio appellate court held that OVC and Consolidated were liable to Columbia for those preventative measures.

Matter of Red Hook 160 LLC v. Borough Constr. Grp. LLC, No. 524909/18, 2019 BL 122210 (N.Y. Sup. Ct. Mar. 19, 2019)

This cases arises out of a project owner’s request for further itemization of amounts claimed in a construction manager’s mechanic’s lien.  Red Hook 160 LLC (“Red Hook”), the owner of the property sought to be liened, demanded a revised itemized statement of the mechanics’ lien filed by Borough Construction Group, LLC (“BCG”), the construction manager hired in connection with the construction and renovation of a six story building located at 160 Imlay Street in Kings County, New York.

Tampa D Fluor Enterprises, Inc. v. Duke Energy Florida, LLC, No. 8:19-cv-00224, 2019 BL 135007, at *1 (M.D. Fla. Apr. 16, 2019)

On April 16, 2019, a Florida federal court dismissed without prejudice Fluor Enterprises’ claim that Duke Energy wrongfully drew down a $67 million letter of credit issued in connection with Fluor’s construction of a gas-fired electrical generation facility in Citrus County, Florida.  In addition to the core breach of contract claim which suffered from several procedural issues, the court dismissed extra-contractual claims for conversion, civil theft, breach of the implied covenant of good faith and fair dealing, and violation of the Florida Deceptive and Unfair Trade Practices Act.

James Talcott Construction, Inc. v. United States, No. 14-427 C, 2019 BL 72711, at *1 (Fed. Cl. Mar. 4, 2019)

In May of 2010, the United States, acting through the Department of Defense (the “Government”) awarded a contract to James Talcott Construction, Inc. (“Talcott”) to replace existing housing for military families at the Malmstrom Air Force Base in Great Falls, Montana.  Talcott was required to construct thirteen buildings, each comprising seventy housing units.  Each building was to be constructed with concrete foundations and wood framing, and the project’ design called for wooden floor joists and subfloor decking to be enclosed in crawlspaces.  The contract stated that the “structural drawings and specification represent the finished structure… [but] do not indicate the method of construction.  The contractor will provide all measures necessary to protect the structure during construction.”  The plans and specifications were silent as to ventilation of the crawlspaces.

Skyrise Construction Group, LLC v. Annex Construction, LLC, 2019 BL 55071 (E.D. Wis. Feb. 20, 2019)

Subcontractor Skyrise Construction, Inc. (“Skyrise”) sued general contractor Annex Construction, Inc. (“Annex”) for breach of contract, promissory estoppel, negligent misrepresentation, and violations of Wisconsin and Illinois trade practices statutes.  Skyrise primarily based its claims on an assertion that the parties entered into a subcontract, which Annex breached when it removed Skyrise from the project and completed the work with an alternative subcontractor.  Both Skyrise and Annex filed motions for summary judgment.  The District Court denied Skyrise’s motion and granted Annex’s motion.

Dep’t of Transp. v. Seattle Tunnel Partners, 2019 BL 36988, 2 (Wash. App. Div. 2 Feb. 05, 2019)

On January 8, 2019, the Court of Appeals for the State of Washington reversed and remanded in part a trial court’s grant of summary judgment in a tunnel-boring construction case.  Specifically, the Court clarified that the three-year statute of limitations for negligence claims begins to run as soon as the aggrieved party becomes aware of the factual elements of the claims.  It does not matter whether the underlying cause of the claims remains disputed.

This article was published in Law360 on March 11, 2019. © Copyright 2019, Portfolio Media, Inc., publisher of Law360. It is republished here with permission.

In 2008, the U.S. Supreme Court in Hall Street Associates LLC v. Mattel Inc. determined that parties may not contractually agree to expand judicial

Servidone, Inc./B. Anthony Constr. Corp., J.V. v. State of New York, No. 2016-05238, 2019 BL 7232 (App. Div., 2d Dept. Jan. 09, 2019)

Servidone, Inc./B. Anthony Construction Corp., J.V. (the “Contractor”) and the New York State Department of Transportation (the “DOT”) entered into a construction contract to reconstruct and replace bridges on Route 59 in New York State. The Contractor retained L.M. Sessler Excavating & Wrecking, Inc. (the “Subcontractor”) to perform the demolition and disposal portion of the project.