Like much of the western and southwestern U.S., California has experienced drought conditions on and off for decades. Fortunately, the regulatory landscape is starting to catch up with water treatment technology, paving the way for states and localities to effectively create a new and reliable supply of potable water.

Since

Fed. Eng’rs & Constructors Inc. v. Relyant Global LLC, No. 3:19-CV-73-KAC-JEM, 2022 U.S. Dist. LEXIS 95617 (E.D. Tenn., May 27, 2022)

This case arises out of the renovation of a U.S. Air Force dormitory in Missouri. The U.S. Army Corps of Engineers hired Relyant Global LLC to act as the prime contractor. Relyant subcontracted with Federal Engineers and Constructors, Inc. (FE&C). Relyant later terminated its subcontract with FE&C. FE&C filed suit against Relyant, and Relyant moved for judgment on the pleadings.

Entech Engineering, P.C. v. Dewberry Engineers, Inc., 204 A.D.3d 467, 167 N.Y.S.3d 55 (1st Dep’t 2022)

The New York Supreme Court Appellate Division recently affirmed a ruling enforcing a pay-if-paid provision.

Defendant Dewberry Engineers, Inc. (Dewberry) contracted with the New York City Economic Development Corporations’ Build-It- Back Hurricane Sandy Program to inspect homes for structural, asbestos, and lead paint issues. Dewberry retained Entech Engineering PC (Entech) to perform pre-construction lead paint inspections of homes. The subcontract contained a pay-if-paid clause that made the city’s payment to Dewberry a condition precedent to Dewberry’s obligation to pay Entech.

On February 28, the New York Senate passed Bill S8430A to amend New York’s Real Property Actions and Proceedings Law Section 881. The current version of Section 881, enacted in 1968, offers a developer judicial recourse when an owner or lessee of a neighboring building refuses access that a developer needs to improve or repair its own building. This judicial recourse comes in the form of a temporary license for access. Section 881 provides limited guidance on how or when courts will issue these temporary licenses, stating only that a “license shall be granted by the court in an appropriate case upon such terms as justice requires.” Over the years, New York courts have filled in the contours of Section 881, providing additional rules for what temporary licenses may cover and when they may be granted. These cases address topics, ranging from required liability insurance to compensation for a landowner’s loss of quiet enjoyment of their property.

In All Seasons Landscaping, Inc. v. Travelers Cas. & Sur. Co. of Am., a Connecticut court considered for the first time whether the performance of warranty work tolls the statute of limitations on payment bond claims. The court ruled that it does not. It dismissed subcontractor All Seasons Landscaping, Inc.’s (ALS’s) bond claim because ALS admitted that it last performed non-warranty work on the project more than one year before filing suit, meaning the statute of limitations barred its claim.

Industrial Steel Construction, Inc. v. Lunda Construction Company, 33 F.4th 1038, 1041 (8th Cir. 2022)

This federal case relates to the construction of a bridge over the Mississippi River between Iowa and Illinois. The state of Iowa hired Lunda Construction Company (Lunda) as the general contractor for the project, which contracted Industrial Steel Construction, Inc. (ISC) to fabricate the structural steel for the bridge. A breach of contract dispute arose between Lunda and ISC that resulted in an arbitration pursuant to the contractual dispute resolution provisions. The arbitrator ruled entirely in favor of Lunda, including awarding Lunda its attorneys’ fees and expert costs, and requiring ISC to reimburse Lunda for its half of the cost of the arbitration.

2700 Bohn Motor, LLC v. F.H. Myers Construction Corp., 338 So.3d 500 (La. Ct. App. 2022).

This case involved the restoration of an old building in New Orleans. Fire broke out, resulting in a loss that was paid by the owner’s builder’s risk insurance. The builder’s risk carriers — subrogated to the rights of the owner — then sued the prime contractor, its subcontractor, and sub-subcontractor for negligence.

Hanuman Chalisa, LLC v. BoMar Contr., Inc., 2022-Ohio-1111, 187 N.E.3d 1108 (Ct. App.)

Hanuman Chalisa LLC (owner) contracted BoMar Contracting, Inc. (BoMar) to construct a hotel in Columbus, OH. The contract consisted of the AIA A101-2007 and AIA A201-2007. The owner later terminated BoMar, alleging deficiencies in BoMar’s work. The parties disputed whether the owner terminated the contract “for cause” or “for convenience.”

RKI Expl. & Prod., LLC v. Ameriflow Energy Servs., LLC, No. 02-20-00384-CV, 2022 Tex. App. LEXIS 4331 (Tex. App. June 23, 2022)

A recent decision by the Court of Appeals of Texas highlights the perils of failing to properly assert a demand for contractual indemnity.

In 2014, a piece of equipment, known as a sand separator, exploded at an oil well in Loving County, TX, killing two individuals and injuring three others. RKI Exploration & Production LLC operated the oil well. RKI contracted with Ameriflow Energy Services LLC and Crescent Services LLC through two master service agreements (MSAs) and a series of work orders.