Introduction

As the nation’s largest energy consumer, the U.S. federal government plans to curb greenhouse gas emissions across its expansive portfolio of more than 350,000 federal buildings.[1] In a pioneering move, the Biden administration and Department of Energy (DOE) recently announced the Climate Smart Buildings Initiative (CSBI).[2] This bold initiative aims to upgrade federal buildings across the U.S. with emerging and sustainable technologies in an effort to meet the Biden administration’s Federal Building Performance Standard, which sets an ambitious goal to cut energy use and electrify equipment and appliances in 30%of the building space owned by the federal government by 2030.[3]Continue Reading U.S. Government Plans to Leverage P3s to Make Federal Buildings More Energy Efficient

Bean Sprouts LLC v. LifeCycle Construction Servs. LLC, No. 001268-CV-2021 (Pa. Super. Feb. 17, 2022)

The Superior Court of Pennsylvania recently raised the bar for state courts to assert jurisdiction over out-of-state defendants in actions brought by residents arising from out-of-state projects.Continue Reading Pennsylvania Appellate Court Affirms Dismissal of In-State Subcontractor’s Suit Against Out-of-State General Contractor for Lack of Jurisdiction, Despite “Long-Term and Ongoing Contractual Relationships”

When is it going to return to “normal”? We all have been asking that question. Well, for the construction industry, it may never return to “normal.” COVID-19 may have permanently changed the landscape of the construction industry in many ways. Depending on your perspective, many changes could be for the better. We may have to alter how we do business to address some new issues and business concerns. Here are just a few issues that the pandemic has brought to the forefront of our industry.
Continue Reading Subtle (and Not So Subtle) Effects of COVID-19 on the Construction Industry

United States Army Corps of Engineers v. John C. Grimberg Co., Inc., No. 2019-1608, 2020 BL 215269 (Fed. Cir. June 9, 2020)

The Court of Appeals for the Federal Circuit reversed a decision by the Armed Services Board of Contract Appeals (“Board”), which had found in favor of a contractor on a Type I differing site condition claim. The Board had held that, even though the contractor’s interpretation of the contract documents was unreasonable, it was more reasonable than the government’s. The Federal Circuit reversed, holding, as a matter of law, that the contractor’s unreasonable interpretation of the contract documents barred its claim.
Continue Reading Federal Court Holds the Reasonableness of the Government’s Interpretation of Geotechnical Data is Irrelevant to Differing Site Condition Claim

COVID-19 has created a severe disruption to the construction industry. Certain jurisdictions, including Boston, San Francisco and Pennsylvania, have placed restrictions on construction projects deemed “nonessential” and require waivers for certain projects to continue. Owners, contractors, suppliers and others may currently have more questions than answers. This article addresses some important concerns, and provides links to additional resources that more specifically address these concerns.
Continue Reading COVID-19 and the Construction Industry: Important Considerations

This article was originally published on December 3, 2019 on ConsensusDocs. It is reprinted here with permission.

Construction contracts often include a “no damage for delay” clause that denies a contractor the right to recover delay-related costs and limits the contractor’s remedy to an extension of time for noncontractor-caused delays to a project’s completion date. Depending on the nature of the delay and the jurisdiction where the project is located, the contractual prohibition against delay damages may well be enforceable. This article will explore whether an enforceable no-damage-for-delay clause is also a bar to recovery of “acceleration” damages, i.e., the costs incurred by the contractor in its attempt to overcome delays to the project’s completion date.Continue Reading Does a No-Damage-for-Delay Clause Also Preclude Acceleration Damages?

Chinese Hosp. Ass’n v. Jacobs Eng’g Grp., Inc., 2019 BL 330340, 2 (N.D. Cal. Sept. 03, 2019)

This case arises out of the alleged breach of contract and defective design for the construction of a new hospital in San Francisco.  During construction, property owner and plaintiff Chinese Hospital Association (“Chinese Hospital”) became aware of alleged defects involving the designs provided by its subcontractor, architect-defendant Jacobs Engineering Group, Inc. (“Jacobs”).  Chinese Hospital terminated its contract with Jacobs for convenience mid-construction.Continue Reading Owner Did Not Waive Right to Damages by Terminating Design Contract for Convenience

Skanska USA Building, Inc. v. J.D. Long Masonry, Inc., No. 1:16-cv-00933, 2019 BL 336852, (D. Md. Sept. 9, 2019)

On September 9, 2019, a Maryland federal court awarded Skanska USA Building, Inc. (“Skanska”) compensatory damages, pre- and post-judgment interest, and litigation expenses including attorney and expert fees in its suit against subcontractor J.D. Long Masonry, Inc. (“Long”) for defective masonry work at a Johns Hopkins University research facility.Continue Reading Maryland Federal Court Upholds Contractual Indemnity Clause and Awards Judgment Interest and Attorneys Fees in Masonry Suit

MBlock Investors, LLC v. Bovis Lend Lease, Inc., etc., et al., 44 Fla. L. Weekly d1432 (3d DCA 2019)

A Florida Appellate Court recently reversed a trial court’s decision granting summary judgment finding an issue of fact based upon an expert affidavit.  The underlying matter involved an action by MBlock Investors against Lend Lease (US) Construction, Inc. for latent defects following MBlock’s acquisition of a property commonly known as the Midblock Miami East Project (the “Property”).Continue Reading Florida Court of Appeals Permits Successor-In-Interest to Pursue Claims Originally Thought to Be Barred by Settlement Agreement