This article was originally published on December 3, 2019 on ConsensusDocs. It is reprinted here with permission.

Construction contracts often include a “no damage for delay” clause that denies a contractor the right to recover delay-related costs and limits the contractor’s remedy to an extension of time for noncontractor-caused delays to a project’s completion date. Depending on the nature of the delay and the jurisdiction where the project is located, the contractual prohibition against delay damages may well be enforceable. This article will explore whether an enforceable no-damage-for-delay clause is also a bar to recovery of “acceleration” damages, i.e., the costs incurred by the contractor in its attempt to overcome delays to the project’s completion date.Continue Reading Does a No-Damage-for-Delay Clause Also Preclude Acceleration Damages?

Chinese Hosp. Ass’n v. Jacobs Eng’g Grp., Inc., 2019 BL 330340, 2 (N.D. Cal. Sept. 03, 2019)

This case arises out of the alleged breach of contract and defective design for the construction of a new hospital in San Francisco.  During construction, property owner and plaintiff Chinese Hospital Association (“Chinese Hospital”) became aware of alleged defects involving the designs provided by its subcontractor, architect-defendant Jacobs Engineering Group, Inc. (“Jacobs”).  Chinese Hospital terminated its contract with Jacobs for convenience mid-construction.Continue Reading Owner Did Not Waive Right to Damages by Terminating Design Contract for Convenience

Westfield Ins. Co. v. Weaver Cooke Constr., LLC, 2019 BL 129431 (E.D.N.C. Apr. 11, 2019)

This case arises out of the alleged defective construction of a condominium complex in North Carolina.  In 2009, the developer on the project filed suit for the alleged construction defects.  This related coverage lawsuit then ensued between the parties’ insurers regarding a duty to defend the general contractor.Continue Reading Federal Court in North Carolina Enforces Insurers’ Duty to Defend a General Contractor as an Additional Named Insured Under the Subcontractor’s Commercial General Liability Policy

Dep’t of Transp. v. Seattle Tunnel Partners, 2019 BL 36988, 2 (Wash. App. Div. 2 Feb. 05, 2019)

On January 8, 2019, the Court of Appeals for the State of Washington reversed and remanded in part a trial court’s grant of summary judgment in a tunnel-boring construction case.  Specifically, the Court clarified that the three-year statute of limitations for negligence claims begins to run as soon as the aggrieved party becomes aware of the factual elements of the claims.  It does not matter whether the underlying cause of the claims remains disputed.Continue Reading The Washington Court of Appeals Clarifies When the Statute of Limitations for a Negligence Claim Begins to Run Under the Discovery Rule