Entech Engineering, P.C. v. Dewberry Engineers, Inc., 204 A.D.3d 467, 167 N.Y.S.3d 55 (1st Dep’t 2022)

The New York Supreme Court Appellate Division recently affirmed a ruling enforcing a pay-if-paid provision.

Defendant Dewberry Engineers, Inc. (Dewberry) contracted with the New York City Economic Development Corporations’ Build-It- Back Hurricane Sandy Program to inspect homes for structural, asbestos, and lead paint issues. Dewberry retained Entech Engineering PC (Entech) to perform pre-construction lead paint inspections of homes. The subcontract contained a pay-if-paid clause that made the city’s payment to Dewberry a condition precedent to Dewberry’s obligation to pay Entech.