Winger Contr. Co. v. Cargill, Inc., No. 17-1169, 2019 BL 132092 (Iowa Apr. 12, 2019).

On April 12, 2019, the Iowa Supreme Court affirmed a lower court ruling which held that, inter alia, the Iowa mechanic’s lien statute would not permit the attachment of mechanic’s liens to the property of a lessor in connection with a contract to supply materials and labor to a lessee.

Aquatherm, LLC v. CentiMark Corp, 2019 BL 13240 (D. Utah Apr. 12, 2019)

Stag II Lindon LLC and Stag Industrial Inc. (collectively “Stag”) owned a building in Lindon, Utah.  Stag contracted with CentiMark Corp. (“CentiMark”) to perform work on the building’s roof.  CentiMark’s work required it to manipulate, move, and reinstall existing heating cables on the roof.  Shortly after completion of the work, in March of 2014, a fire occurred on the roof which was traced to the location of heat tape, which CentiMark had removed and replaced.

EnerQuest Oil & Gas, L.L.C. v. Antero Resources Corporation, No. 02-18-000178CV, 2019 BL 130860 (Tex. App. – Fort Worth Apr. 11, 2019)

A Texas appellate court recently found that an out-of-state Oklahoma-based limited liability company was not subject to personal jurisdiction in Texas for alleged misappropriation of trade secrets claims.

Westfield Ins. Co. v. Weaver Cooke Constr., LLC, 2019 BL 129431 (E.D.N.C. Apr. 11, 2019)

This case arises out of the alleged defective construction of a condominium complex in North Carolina.  In 2009, the developer on the project filed suit for the alleged construction defects.  This related coverage lawsuit then ensued between the parties’ insurers regarding a duty to defend the general contractor.

A.E. Rosen Elec. Co. v. Plank, LLC, No. 07862-7, 2019 BL 113951 (Sup. Ct. Mar. 01, 2019)

On March 1, 2019, the Supreme Court of New York, Albany County, granted a subcontractor’s motion for summary judgment on a payment dispute involving a “pay-when-paid” contract provision.

Defendant Plank, LLC (“Contractor”) entered into a construction contract with Dutch Village, LLC (“Owner”) to act as the general contractor for the construction of four apartment buildings (“Project”).  Thereafter, Contractor entered into a subcontract with Plaintiff A.E. Rosen Electrical, Inc. (“Subcontractor”) for electrical work on the Project.  After nine months of work on the Project, a payment dispute arose between the Owner and Contractor.  At that time, Contractor directed the Subcontractor to cease work on the Project.

Arco Ingenierosm, S.A. v. CDM Int’l Inc., Civil Action No. 18-12348-PBS, 2019 BL 100779 (D. Mass. Mar. 22, 2019)

In November 2009, Tropical Storm Ida hit El Salvador, causing flooding, landslides, and the destruction of homes, roads, bridges, schools, health clinics, and other infrastructure.  The United States Agency for International Development (“USAID”) provided $25 million in funding to rebuild damaged infrastructure.  USAID retained Defendant CDM International Inc. (“CDM”) to conduct studies and assessment for the construction of eight schools and one health clinic (the “Projects”) and to create preliminary designs and technical specifications for these Projects.  These preliminary designs were intended to constitute at least thirty percent of final designs for the Projects.  Relying on the preliminary designs created by CDM, Plaintiff Arco Ingenieros, S.A. de C.V. (“ARCO”) submitted bids to act as the design-build contractor for the Projects.  USAID awarded the Projects to ARCO.

Team Contractors, LLC v. Waypoint Nola, LLC, No. 16-1131, 2019 BL 96133 (E.D. La. Mar. 20, 2019)

The Eastern District of Louisiana recently denied the motion of a prime contractor (the “Contractor”) for summary judgment on its breach of contract claim against the owner (the “Owner”) of a construction project in New Orleans (the “Project”) where the primary issue involved whether a suspensive condition was enforceable.

SMJ Gen. Constr., Inc. v. Jet Commer. Constr., LLC, No. S-16785/16985, 2019 BL 131640 (Alaska Apr. 12, 2019)

In 2016, Jet Commercial Construction, LLC (“Jet”) entered into a subcontract with SMJ General Construction, Inc. (“SMJ”) to supply materials and labor for the construction of a restaurant in Hawaii.  The subcontract contained a dispute resolution provision that required the parties to first mediate any dispute and then submit it to arbitration if mediation was unsuccessful.  It also included a choice-of-law and venue provision designating Oklahoma Law and the courts of Cleveland County, Oklahoma for any lawsuits pertaining to the Agreement’s enforcement.

R&O Constr. Co. v. MBA Gen. Contracting, LLC, No. 1:18-cv-00042, 2019 BL 98680 (D. Utah Mar. 21, 2019)

On March 21, 2019, a Utah federal court granted Defendants MBA General Contracting, LLC and Cory Martin’s motion to dismiss R&O Construction Company’s claim for attorney fees.
R&O, as general contractor of a construction project, entered into two subcontracts with MBA to perform concrete work.  The first subcontract, entitled Master Subcontract Agreement, outlined general obligations between the parties.  The second, entitled Work Authorization Document, outlined more specific obligations.  R&O asserted various causes of action against MBA arising from MBA’s alleged breach of the subcontracts, including a claim for attorney fees.  MBA moved to dismiss the attorney fees claim, arguing that neither subcontract provides for such an award.

Matter of Red Hook 160 LLC v. Borough Constr. Grp. LLC, No. 524909/18, 2019 BL 122210 (N.Y. Sup. Ct. Mar. 19, 2019)

This cases arises out of a project owner’s request for further itemization of amounts claimed in a construction manager’s mechanic’s lien.  Red Hook 160 LLC (“Red Hook”), the owner of the property sought to be liened, demanded a revised itemized statement of the mechanics’ lien filed by Borough Construction Group, LLC (“BCG”), the construction manager hired in connection with the construction and renovation of a six story building located at 160 Imlay Street in Kings County, New York.