Gainesville Mech., Inc. v. Air Data, Inc., No. A19A0518., 2019 BL 229069 (Ga. Ct. App. June 19, 2019)

The First Division of the Georgia Court of Appeals affirmed a superior court’s decision to confirm an arbitration award against Appellant Gainesville Mechanical, Inc. (“Gainesville”) because Gainesville failed to show that the arbitrator manifestly disregarded the law governing the “modified total cost” approach to damages.Continue Reading Georgia Court of Appeals Affirms Superior Court’s Confirmation of Arbitration Award, Finding That Arbitrator Did Not Manifestly Disregard Law Governing the “Modified Total Cost” Approach to Damages

Rad and D’Aprile, Inc. v. Arnell Construction Corp, No. 502464/14, 2019 BL 131606 (NY. Sup. Ct. April 3, 2019)

In June of 2001, Arnell Construction Corp. (“Arnell”) entered into a prime contract to build two sanitation garages in Brooklyn for the New York City Department of Sanitation (the “City”).  Arnell subcontracted the project’s masonry work to Rad and D’Aprile, Inc. (“Rad”).  After execution of the subcontract, Rad was informed that the start of work would be delayed because the City had not yet obtained ownership or access to all portions of the site.  When its work did commence, only limited portions of the site were available.  This caused inefficiencies in Rad’s work and caused it to incur increased costs.Continue Reading New York Court Holds Contractor’s Failure to Timely Pass Through Subcontractor Delay Claim to the Owner Constitutes Breach of the Covenant of Good Faith and Fair Dealing

Aquatherm, LLC v. CentiMark Corp, 2019 BL 13240 (D. Utah Apr. 12, 2019)

Stag II Lindon LLC and Stag Industrial Inc. (collectively “Stag”) owned a building in Lindon, Utah.  Stag contracted with CentiMark Corp. (“CentiMark”) to perform work on the building’s roof.  CentiMark’s work required it to manipulate, move, and reinstall existing heating cables on the roof.  Shortly after completion of the work, in March of 2014, a fire occurred on the roof which was traced to the location of heat tape, which CentiMark had removed and replaced.Continue Reading District Court in Utah Grants Summary Judgment for Contractor Against Insurance Subrogation Claim Based on Contractual Waiver Provision and Statute of Limitations

Westfield Ins. Co. v. Weaver Cooke Constr., LLC, 2019 BL 129431 (E.D.N.C. Apr. 11, 2019)

This case arises out of the alleged defective construction of a condominium complex in North Carolina.  In 2009, the developer on the project filed suit for the alleged construction defects.  This related coverage lawsuit then ensued between the parties’ insurers regarding a duty to defend the general contractor.Continue Reading Federal Court in North Carolina Enforces Insurers’ Duty to Defend a General Contractor as an Additional Named Insured Under the Subcontractor’s Commercial General Liability Policy

Whiting-Turner Contracting Co. v Guar. Co. of N. Am. USA, 2019 BL 97923 (Colo. App. Mar. 21, 2019).

This construction dispute involved rights and obligations under a performance bond supplied for an office building construction project in Denver, Colorado.  Whiting-Turner Contracting Company was the general contractor, and it subcontracted Klempco Construction to construct an anchor system for the project’s underground parking garage.  Klempco provided performance and payment bonds for the project from Guarantee Company of North America USA (“GCNA”).  When Klempco fell behind schedule, it stopped paying its sub-subcontractors and directed Whiting-Turner to assume responsibility for its work and sub-subcontractors.Continue Reading Colorado Court of Appeals Finds Contractor Satisfied Conditions Precedent Under Performance Bond

Team Contractors, LLC v. Waypoint Nola, LLC, No. 16-1131, 2019 BL 96133 (E.D. La. Mar. 20, 2019)

The Eastern District of Louisiana recently denied the motion of a prime contractor (the “Contractor”) for summary judgment on its breach of contract claim against the owner (the “Owner”) of a construction project in New Orleans (the “Project”) where the primary issue involved whether a suspensive condition was enforceable.Continue Reading Federal Court in Louisiana Upholds Suspensive Condition Not Subject Solely to Owner’s Whim

R&O Constr. Co. v. MBA Gen. Contracting, LLC, No. 1:18-cv-00042, 2019 BL 98680 (D. Utah Mar. 21, 2019)

On March 21, 2019, a Utah federal court granted Defendants MBA General Contracting, LLC and Cory Martin’s motion to dismiss R&O Construction Company’s claim for attorney fees.
R&O, as general contractor of a construction project, entered into two subcontracts with MBA to perform concrete work.  The first subcontract, entitled Master Subcontract Agreement, outlined general obligations between the parties.  The second, entitled Work Authorization Document, outlined more specific obligations.  R&O asserted various causes of action against MBA arising from MBA’s alleged breach of the subcontracts, including a claim for attorney fees.  MBA moved to dismiss the attorney fees claim, arguing that neither subcontract provides for such an award.Continue Reading Utah Federal Court Dismisses Claim for Attorney Fees Finding That Neither the Indemnification Provision nor the Failure-To-Perform Provision Applies to a Lawsuit Between Contractor and Subcontractor

Columbia Gas Transmission, LLC v. Ohio Valley Coal Co., 2019 BL 99544 (Ohio Ct. App. Mar. 21, 2019)

Columbia Gas Transmission, LLC (“Columbia”) operated a high-pressure gas pipeline.  A portion of pipeline crossed land for which Ohio Valley Coal Company (“OVC”) and Consolidated Land Company (“Consolidated”) held interest rights in the underlying coal.  Columbia undertook measures to protect its pipeline from subsidence damage that OVC’s subterranean coal mining was certain to cause.  An Ohio appellate court held that OVC and Consolidated were liable to Columbia for those preventative measures.Continue Reading Ohio Appellate Court Finds That Coal Mining Entities Are Liable to Pipeline Operator for Preventative Measures to Protect Against Subsidence Damages

Dep’t of Transp. v. Seattle Tunnel Partners, 2019 BL 36988, 2 (Wash. App. Div. 2 Feb. 05, 2019)

On January 8, 2019, the Court of Appeals for the State of Washington reversed and remanded in part a trial court’s grant of summary judgment in a tunnel-boring construction case.  Specifically, the Court clarified that the three-year statute of limitations for negligence claims begins to run as soon as the aggrieved party becomes aware of the factual elements of the claims.  It does not matter whether the underlying cause of the claims remains disputed.Continue Reading The Washington Court of Appeals Clarifies When the Statute of Limitations for a Negligence Claim Begins to Run Under the Discovery Rule

Team Contrs., L.L.C. v. Waypoint NOLA, L.L.C., No. 16-1131, 2017 U.S. Dist. LEXIS 162172 (E.D. La. Oct. 2, 2017).

Waypoint NOLA (“Waypoint”) was the owner of a hotel construction project in New Orleans (the “Project”).  Waypoint contracted with Team Contractors (“Team”) to serve as the Project general contractor and HC Architecture (“HCA”) to serve as the Project architect.  HCA, in turn, subcontracted with KLG to prepare the mechanical, electrical, and plumbing (“MEP”) plans.

HCA delivered a complete set of specifications, including KLG’s MEP plans, to Team, and Team began work.  It was later discovered that the MEP plans did not comply with code requirements.  Team was forced to remove and reconstruct the MEP work before proceeding with its work as scheduled.
Team filed suit for breach of contract against Waypoint and for negligence against Waypoint, HCA, and KLG.  Team alleged it experienced delay and incurred damages when it was forced to remove and reconstruct the MEP work.  Its damages included extended home office overhead related to the delay.  Team’s expert used the Eichleay formula to calculate these damages.Continue Reading Federal Court Holds That, Under Louisiana Law, a Contractor Need Not Show a Total Work Stoppage to Recover Extended Home Office Overhead Under Eichleay