City of Lonsdale v. NewMech Companies, Inc.
2008 Minn. App. Unpub. LEXIS 31 (Minn. App. 2008)
The City of Lonsdale solicited sealed bids for construction of a wastewater-treatment plant. According to the terms of the bid form, each bidder submitting a bid form:
“Propose[d] and agree[d], if [the] Bid is accepted, to enter into an Agreement with City in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in the Bid and in accordance with the other terms and conditions of the Bidding Documents.”

WM Hotel Group, LLC v. Pride Construction, Inc.
2008 R.I.Super.LEXIS 9 (2008)
WM Hotel, owner of the Hampton Inn & Suites, located in Middletown, R.I. initiated a lawsuit against Pride Construction, the general contractor for the construction of its hotel, Antcil Plumbing & Mechanical Contractors, Inc., the plumbing subcontractor that installed the hotel bathtubs and Travelers, Antcil’s insurer under a CGL policy.
Antcil installed the tubs, tested them for leaks, placed “tub protectors” in each and transferred control of them to Pride. The tubs began evidencing cracking, rust, and sagging. WM Hotel asserted that 93 of the 95 tubs were defective as manufactured and/or installed and that it was Antcil’s faulty installation that resulted in the damage to the tubs. Forensic testing and analysis indicated that a styrofoam sound deadening pad was missing from beneath the tubs, and that the omission could have contributed to deflection of the bathing surface. Travelers filed a motion for summary judgment asserting that the CGL policy issued on behalf of Antcil did not provide coverage for the damage incurred. Travelers asserted that the damages were not the result of an “occurrence” as defined in the policy and that exclusionary language in the policy precluded coverage.

Metric Construction Co., Inc. v. United States
2008 U.S. Claims LEXIS 5 (Fed. Cl., Jan. 7, 2008)
Metric Construction was awarded the contract to construct a warehouse for the United States Army Corps of Engineers at an Air Force base in Utah. After the roof developed serious leaks, the Corps required Metric to replace the roof. Metric then submitted a request for equitable adjustment in the amount of $2,173,091.85 for costs incurred in repairing water damage caused by the leaks, replacing damaged property in the warehouse, and installing a new roof, under the theory that the Corps’ design specifications for the structural steel underlying the roof were defective, and that defective specifications and the Corps’ communications with Metric regarding the roof installation were misrepresentations on which Metric relied to its detriment.

1800 Ocotillo, LLC v. WLB Group, Inc.
2008 Ariz. App. LEXIS 9 (Jan. 29, 2008)
The Court of Appeals of Arizona held that a state statute prohibiting design professionals for contracting for indemnity for their sole negligence does not as matter of law prohibit the use of limitation of damages provisions in professional service contracts.
In 1998, a real estate developer, 1800 Ocotillo, undertook the development of a townhouse project in Phoenix that bordered the Arizona Canal. Developer hired an engineering-architectural firm, The WLB Group, to perform surveying, engineering and landscape architecture services on the project. Developer had its design-build contractor sign the contract with the engineering-architectural firm, which included a limitation of damages provision limiting its exposure to the amount of its fees. While the parties never specifically discussed this provision, the entire contract was incorporated into a supplemental contract between the Developer and the engineering architectural firm approximately two years later.

Argonaut Great Cent. Ins. Co. v. DiTocco Konstruction, Inc.
2007 U.S. Dist. LEXIS 93846 (D.N.J. Dec. 21, 2007)
After a fire destroyed a T.G.I. Friday’s restaurant and all of its equipment, the meaning of the subrogation continuation clause contained in the contract between the owner and the contractor who had performed renovations and remodeling of the restaurant five years earlier became the focal point of ensuing dispute.

Jalapenos, LLC v. GRC General Contractor, Inc.,
2007 PA Super 391, 2007 Pa. Super. LEXIS 4411 (Dec. 19, 2007)
Jalapenos, LLC, hired GRC General Contractor, Inc. to remodel a restaurant. The parties signed standard American Institute of Architects contracts (AIA Forms A101 and A201 – 1997). Under the contract, Jalapenos was required to obtain Builder’s Risk “all-risk” property insurance or equivalent, or inform the contractor in writing before the work began if it did not intend to purchase such insurance. Furthermore, if GRC was damaged by Jalapenos’ failure to maintain the required insurance without notifying GRC, then Jalapenos would be liable for all reasonable costs attributable to such failure.

Steel Services Corp. v. Board of County Commissioners
2007 U.S. App. Lexis 30052 (6th Cir. Dec. 27, 2007)
The Cincinnati Reds were building a new baseball stadium. Hamilton County (“County”) awarded Contractor, Steel Service Corp. (“Contractor”), a $33 million dollar contract for the fabrication and erection of the steel superstructure. The start of the Contractor’s work was delayed. The County’s construction manager directed the Contractor to accelerate its work due to the project delays and take extraordinary measures to comply with the contract and schedule. Contractor accelerated and submitted a claim for additional costs incurred by itself and its subcontractors. The County and Contractor executed a change order providing for a provisional payment to be applied against the amount, if any, to which the Contractor was ultimately determined to be entitled in reimbursement of the acceleration costs. Neither party accepted responsibility for the delays in the change order. The change order stated that Contractor had begun implementing extraordinary measure, had incurred additional costs and would continue to do so throughout the course of the project. Construction proceeded.

U.S. ex rel. Platinum Mechanical, LLC v. U.S. Surety. Co.
07 Cv. 3318(CLB), 2007 U.S. Dist. LEXIS 94026( S.D.N.Y. Dec. 21, 2007)
CFP Group, Inc. was awarded a contract with the United States Government to refurbish facilities at Stewart Air National Guard Base in New York. Platinum Mechanical, LLC subcontracted to perform all of the plumbing and HVAC work for the Project. All work on the Project was to be completed by March 12, 2007. Notice to proceed issued on June 14, 2006.

Tennessee Gas Pipeline Co. v. Technip USA Corp.
2007 Tex. App. LEXIS 9951, No. 01-06-00535-CV (Tex. App. Dec. 21, 2007)
The Court of Appeals of Texas for the First District was asked to review a trial court’s limitation of a jury award for damages to only those damages associated with defective work. In making its ruling, the Court of Appeals was asked to assess the extent of a waiver of consequential damages clause and which damages were considered consequential barred by said clause. After overlapping contract provisions and the damages sought, the Court of Appeals found that damages flowing from delay were recoverable so long as they were direct, meaning that they flowed naturally and necessarily from the delay.

United States Fire Insurance Co. v. J.S.U.B., Inc. and Auto-Owners Insurance Co. v. Pozzi Window Co.
2007 Fla. LEXIS 2394 and 2007 Fla. LEXIS 2391 (Dec. 20, 2007)
On December 20, 2007, the Florida Supreme Court decided United States Fire Insurance Company, et al. v. J.S.U.B., Inc., et al., 2007 Fla. LEXIS 2394, and Auto-Owners Insurance Company v. Pozzi Window Company, et al., 2007 Fla. LEXIS 2391 – two cases dealing with whether a standard form CGL policy with products completed operations hazard coverage issued to a general contractor, cover a general contractor’s liability to a third party for repair and/or replacement costs due to defective work by its subcontractor.