BML Properties Ltd. v. China Construction America Inc., et al., 101 N.Y.S. 3d 597 (N.Y. App. Div. 2019)

On July 2, 2019, a New York appellate court upheld a lower court ruling by Justice Saliann Scarpulla, denying a state-backed Chinese contractor’s attempt to compel international arbitration arising out of a dispute involving the construction of the multibillion Baha Mar mega-resort in the Bahamas.  As a result of the ruling in BML Properties Ltd. v. China Construction America Inc., et al., 101 N.Y.S. 3d 597 (N.Y. App. Div. 2019), aff’ing No. 657550/2017 (N.Y. Sup. Ct. Jan. 24, 2019), the $2.25 billion lawsuit alleging “one of the largest construction-based frauds in this hemisphere” will remain in the New York courts.  As explained below, for those in the international construction industry, the case will be worth following.

DAK Americas Mississippi, Inc. v. Jedson Engineering, Inc. et al, No. 1:18cv31-HSO-JCG, 2019 BL 208838 (S.D. Miss. June 6, 2019)

This dispute arose out of the design and construction of a concrete storage slab at DAK’s polymer resin manufacturing facility located in Hancock County, Mississippi.  DAK hired Ohio-based Jedson to design and oversee the construction of a cement slab suitable for commercial operating loaders and other heavy equipment necessary to transport, unload, and stack shipping containers.  DAK allegedly discovered substantial cracking and chipping of the cement, and filed suit in federal court claiming Jedson failed to design a slab suitable for DAK’s intended purposes.  DAK asserted claims for negligent design, negligent construction management, and breach of contract.

Popple Construction, Inc. v. Reilly Associates, Inc. No. 775-MDA-2017, 2019 BL 213236 (Pa. Sup. Ct., June 10, 2019).

On June 10, 2019, the Superior Court of Pennsylvania affirmed a lower court decision to deny a motion to dismiss in connection with a tort claim for negligent misrepresentation by a contractor against a third-party design/engineer.  The Court’s opinion highlights Pennsylvania’s exception to the economic loss doctrine insofar as it applies to claims raised by contractors against architects/engineers for faulty bidding documents, specifications, or designs.

Dolan v. Hurd Millwork Co., No. 2951 EDA 2015, 2019 BL 229344 (Pa. Super. Ct. June 21, 2019)

This cases arises out of defective windows installed in a residential construction project. In 1999, Leo J. Dolan purchased a custom home from Bentley Homes, Ltd. and its affiliates (“Bentley Homes”).  Hurd Millwork Company, Inc. provided many of the home’s windows.   Dolan almost immediately observed issues in the home’s construction, including air and water leaks around the windows.   Bentley Homes, however, led him to believe the issues had been fixed.

Gainesville Mech., Inc. v. Air Data, Inc., No. A19A0518., 2019 BL 229069 (Ga. Ct. App. June 19, 2019)

The First Division of the Georgia Court of Appeals affirmed a superior court’s decision to confirm an arbitration award against Appellant Gainesville Mechanical, Inc. (“Gainesville”) because Gainesville failed to show that the arbitrator manifestly disregarded the law governing the “modified total cost” approach to damages.

Construction disputes frequently require companies to engage third-party consultants to analyze and opine on such issues as delays, defects in workmanship or materials, and deficiencies in payment— even before they anticipate litigation.  Construction companies should keep in mind that materials they provide consultants, and materials that consultants generate, can in

On June 12, 2019, the World Bank announced that China-based Dongfang Electronics Co. Ltd. (“Dongfang”) would be debarred for fifteen (15) months for fraudulently bidding on a $60 million electrical expansion project in Liberia.  The debarment renders Dongfang, a state-owned enterprise specializing in manufacturing and installing electrical equipment in connection with energy and infrastructure projects, ineligible to participate in any projects financed by the World Bank.  Dongfang’s debarment by the World Bank highlights the compliance risks contractors and subcontractors face when pursuing contracts associated with foreign projects financed by institutions such as the World Bank.

Winger Contr. Co. v. Cargill, Inc., No. 17-1169, 2019 BL 132092 (Iowa Apr. 12, 2019).

On April 12, 2019, the Iowa Supreme Court affirmed a lower court ruling which held that, inter alia, the Iowa mechanic’s lien statute would not permit the attachment of mechanic’s liens to the property of a lessor in connection with a contract to supply materials and labor to a lessee.

Aquatherm, LLC v. CentiMark Corp, 2019 BL 13240 (D. Utah Apr. 12, 2019)

Stag II Lindon LLC and Stag Industrial Inc. (collectively “Stag”) owned a building in Lindon, Utah.  Stag contracted with CentiMark Corp. (“CentiMark”) to perform work on the building’s roof.  CentiMark’s work required it to manipulate, move, and reinstall existing heating cables on the roof.  Shortly after completion of the work, in March of 2014, a fire occurred on the roof which was traced to the location of heat tape, which CentiMark had removed and replaced.

Team Contractors, LLC v. Waypoint Nola, LLC, No. 16-1131, 2019 BL 96133 (E.D. La. Mar. 20, 2019)

The Eastern District of Louisiana recently denied the motion of a prime contractor (the “Contractor”) for summary judgment on its breach of contract claim against the owner (the “Owner”) of a construction project in New Orleans (the “Project”) where the primary issue involved whether a suspensive condition was enforceable.