Marenalley Constr., LLC v. Zurich American Ins. Co. and Nason Constr. Inc., 2015 U.S. Dist. LEXIS 30968 (E.D. Pa. March 13, 2015)

This payment dispute case arises out of a Veterans Affairs (“VA”) construction project located in Philadelphia. Nason was the general contractor, Zurich was Nason’s surety, and Marenalley was Nason’s subcontractor. Marenalley’s subcontract required it to pursue any claim related to the project through the administrative disputes resolution process provided by Nason’s prime contract with the VA before bringing suit against the project’s bond.  The prime contract’s administrative dispute resolution process clause incorporated the terms of the Contract Disputes Act (the “CDA”).

KBW Assocs. v. Jaynes Corp., 2015 U.S. Dist. LEXIS 18220 (D. Nev. Feb. 13, 2015)

This action arose out of the construction of additions to existing buildings at Creech Air Force Base in Indian Springs, Nevada (the “Project”).  The United States Army Corps of Engineers (the “COE”) contracted with Defendant Jaynes Corporation, Inc. (“Jaynes”) to perform the work.  Jaynes then subcontracted with Plaintiff, KBW Associates, Inc. (“KBW”), to construct the metal framing and outer shell of the buildings.

Following construction delays, Jaynes found itself involved in two separate actions.  In the first action (the “Prime Contract Litigation”), Jaynes was defending against liquidated damages assessed by the COE under the prime contract.  In the instant action (the “Subcontract Litigation”), Jaynes was defending a Miller Act suit for contract balances brought by KBW.  KBW alleged Jaynes was responsible for the construction delay, through a “pattern of mismanagement”, involving failure to timely approve work, unilateral imposition of work beyond the scope of the subcontract and improper scheduling.  Jaynes asserted several affirmative defenses and filed counterclaims against KBW, on grounds that KBW failed to perform in accordance with the subcontract and failed to meet construction schedules.

An amended version of this post was published in the March 16, 2015 AGC Construction Law in Brief, the weekly newsletter for the Associated General Contractors of America.

Since 1994, Pennsylvania law has provided enhanced remedies for prevailing in a payment dispute arising out of a construction project.  The prevailing party in a recent jury trial discovered uncertainty in the precise contours of those available remedies.  There was no clear precedent governing recovery of fees of a testifying expert, necessary to overcome the complex accounting and delay claims asserted by the defendant in response to the invoice dispute, and the method of calculating pre-judgment and post-judgment interest and penalty interest under the statute.  Because of the large sums at issue, the difference in calculation methods was significant.  Entitlement to these matters was unclear in spite of 20 years of precedent under the Pennsylvania Contractor and Subcontractor Payment Act.

U.W. Marx, Inc. v. Koko Contracting, Inc., No. 518611, 2015 N.Y. App. Div. LEXIS 600 (N.Y. App. Div. Jan. 22, 2015)

The Appellate Division of the Supreme Court of New York affirmed judgment in favor of a subcontractor holding that although the subcontractor failed to comply with a contractual provision requiring it to give timely notice of its intent to stop work due to contractor’s failure to make payment, the contractor’s prior failure to make three consecutive progress payments to subcontractor constituted an uncured, material breach that relieved the subcontractor from performing its remaining obligations under the parties’ contract.

Philadelphia Auth. for Indus. Dev. v. United States, 114 Fed. Cl. 519 (2014)

In this action, the United States Court of Federal Claims denied the Government’s motions to dismiss and for summary judgment, holding that plaintiff had sufficiently pled and supported claims against the Government based upon misrepresentations and omissions in data supplied by the Government in a negotiated procurement.  The Court held that negligent estimate, superior knowledge, misrepresentation and mutual mistake were viable theories upon which to pursue such a claim.  It rejected the Government’s position that a claim for negligent estimate could not be maintained in the context of a negotiated procurement, and also held that the plaintiff’s expectation of a limited loss did not negate the element of reliance with respect to much larger losses attributable to undisclosed or misrepresented information.

Scungio Borst & Assocs. v. 410 Shurs Lane Developers, LLC et al., 2014 Pa. Super. LEXIS 4527 (Pa. Super. Ct. 2014)

On reconsideration of an earlier panel decision of the Pennsylvania Superior Court, the Court en banc rejected a contractor’s contention that Pennsylvania’s Contractor and Subcontractor Payment Act (“CASPA”) extends liability for non-payment beyond the actual contracting parties.

This action arose out of the construction of a condominium project in Philadelphia’s Manayunk neighborhood (the “Project”).  The owner, 410 Shurs Lane Developers, LLC (the “Owner”), entered into a written contract with Scungio Borst & Associates (the “Contractor”) for the construction of the Project.  The Contractor performed the contracted-for construction services, as well as $2.6 million in additional work at the direction of the Owner and the Owner’s President and fifty percent shareholder, Robert DeBolt.  When the Contractor was not paid approximately $1.5 million incurred due to the additional work, it filed suit against the Owner and Mr. DeBolt individually, alleging, inter alia, breach of contract and violation of CASPA.

Frontier Contr. Inc. v. Allen Eng’g Contr., Inc., 2014 U.S. Dist. LEXIS 136474 (E.D. Cal. Sept. 2014)

Frontier Contracting Inc. (Frontier) entered into a teaming agreement with Allen Engineering Contractor, Inc. (Allen) to complete two U.S. Federal Highway projects in Sequoia and Kings Canyon National Parks.  During the course of the projects, disputes arose and Allen refused to issue full payments to Frontier.  Frontier then filed a complaint against Allen alleging, in part, a Miller Act claim.

C. Szabo Contracting, Inc. v. Lorig Construction Co., 2014 IL App (2d) 131328; 2014 Ill. App. LEXIS 699 (Sept. 29, 2014)

In May of 2006, the Illinois State Toll Highway Authority (“Highway Authority”) retained Defendant Lorig Construction Company (“Lorig”) as general contractor on a construction project for improvements to Interstate 355. The Highway Authority required that Lorig subcontract a portion of its work to a “Disadvantaged Business Enterprise” (“DBE”), and that the project be performed with union labor.

When responding to document requests or a subpoena duces tecum, litigants in New York traditionally have been faced with the onerous privilege log requirements set forth in Section 3122 of the New York Civil Practice Law and Rules.  Section 3122 requires a litigant who withholds any responsive documents to provide to the requesting party a privilege log containing a separate entry for each withheld document.  Each entry must disclose the legal grounds on which the document is withheld, in addition to certain identifying information including the type of document, the general subject matter of the document, and the date of the document.  N.Y. CPLR § 3122(b).  In complex construction disputes, there is often a large volume of privileged documents, and thus preparing a privilege log that meets the requirements of Section 3122 can be time consuming and expensive.