On June 16, 2016, the U.S. Supreme Court ruled in the matter of Universal Health Services, Inc. v. United States ex rel. Escobar, 136 S. Ct. 1989 (2016), changing the legal landscape for False Claims Act qui tam claims concerning the implied false certification theory of liability. This article will discuss the Escobar holding and examine relevant considerations for contractors in light of this ruling.
Construction Dispute
Eastern District of Pennsylvania Distinguishes Bilt-Rite in Dispute Involving Information Provided to Designers by Remedial Contractor
Elliott-Lewis Corp. v. Skanksa USA Bldg., Inc., 2016 U.S. Dist. LEXIS 59406 (E.D.Pa. May 4, 2016)
The Federal District Court for the Eastern District of Pennsylvania held that the narrow exception to the economic loss doctrine carved out in Bilt-Rite Contractors, Inc. v. The Architectural Studio – where the Pennsylvania Supreme Court held that architects and other design professionals may be held liable to third parties that rely to their detriment on false information provided in design documents by architects and other design professionals – does not apply to a contractor that supplied information to design professionals in connection with remedial work performed by the contractor.
Court of Appeals of Michigan Holds Contractor Cannot Recover Eichleay Damages from Supplier Absent Contractual Right and Proof that Delay in Delivery Caused an Actual Loss
ITT Water & Wastewater USA, Inc. v. L. D’Agostini & Sons, Inc., 2016 Mich. App. LEXIS 579 (March 17, 2016)
This action arises out of a contract dispute between plaintiff, ITT Water & Wastewater USA, Inc. (“ITT”), and defendant, L. D’Agostini & Sons, Inc./Lakeshore Engineering Services, Inc. Joint Venture (“D’Agostini”), related to ITT’s supply of eight water pumps to D’Agostini on a project to construct a sanitary and storm water treatment and pumping station. D’Agostini filed a counterclaim against ITT, alleging that ITT’s late pump delivery delayed the project by 103 days. The trial court granted ITT’s motion for partial summary disposition and ruled that D’Agostini could not rely upon the Eichleay formula for determining its alleged home office overhead damages. The parties then dismissed, without prejudice, the remaining claims and D’Agostini appealed.
Tennessee Federal District Court Holds That Contractor May Pursue Both Breach of Contract Action in Federal Court and Lien Enforcement Action In State Court – Abstention Not Required
Summit Contracting Grp., Inc. v. Ashland Heights, LP, 2016 U.S. Dist. LEXIS 60662 (M.D. Tenn. May 6, 2016)
Ashland Heights, LP (“Owner”) contracted with Summit Contracting Group, Inc. (“Contractor”) to construct an assisted living facility in Tennessee. After completing the project, Contractor alleged that Owner had failed to pay Contractor in full for the work it performed; to make timely payments; to provide Contractor a time extension for inclement weather; and to deposit retainage into an interest-bearing escrow account as required by Tennessee’s Retainage Law.
Contractor filed a breach of contract and Retainage Law action in federal district court, seeking damages and litigation costs in excess of $1.5 million (the “Contract Action”). Contractor concurrently filed a mechanic’s lien action in state court seeking enforcement of the lien in the amount of $1,074,688.74 (the “Lien Action”).
Texas District Court Rejects Rail Contractor’s Delay and Prompt Payment Claims and Awards Owner More Than $3 Million
Balfour Beatty Rail, Inc. v. The Kansas City Southern Railway Company, 2016 U.S. Dist. LEXIS 39086 (N.D. Tex., March 25, 2016)
The contractor contracted with owner to install 65 miles of railroad track, for a price of $12,206,666. The owner had engaged another contractor to grade and prepare the substrate for the railroad track, and was to furnish and deliver aggregate for track ballast and track rail material to various locations along the rail route. The contractor’s scope included all other work. The contractor fell behind in its work, and the owner hired additional contractors to complete a portion of its scope. The contractor blamed the delays on the owner’s late delivery of aggregate and rail, and improper subgrade preparation under a theory of differing site conditions. It sought $4.35 million in unpaid change orders, delay damages, and penalties under Texas’ prompt payment statutes. The owner in turn sought $2.6 million in completion costs and costs of wasted aggregate.
Pennsylvania Commonwealth Court Holds Enforceable School District’s Oral Promise to Pay Subcontractor for Returning to Job after Prime Contractor’s Termination
Zacherl, Inc. v. Flaherty Mechanical Contractors, LLC, 131 A.3d 1030, 2016 Pa. Commw. LEXIS 22 (Jan. 6, 2016)
The West Allegheny School Board (the “School Board”) voted to approve the School District’s (the “District’s”) plan to renovate its high school building (the “Project”). The District contracted with Flaherty Mechanical Contractors, LLC (“Flaherty”) to act as the prime contractor. Flaherty submitted the names of its subcontractors for the School Board’s review. When the School Board raised no objections to Flaherty’s submission, Flaherty subcontracted with F. Zacherl, Inc. (“Zacherl”) to perform sheet metal work at the Project.
During the Project, the District made timely payments to Flaherty, but Flaherty failed to make timely payments to its subcontractors, including Zacherl. The District terminated Flaherty’s contract in part as a result of Flaherty’s payment issues. Flaherty, in turn, terminated Zacherl’s contract.
Federal Court in Pennsylvania Holds That Contractor’s Nominal Underpayment of Progress Payments Does Not Relieve Subcontractor’s Duty to Perform
Butch-Kavitz, Inc. v. Mar-Paul Co., Inc., 2015 U.S. Dist. LEXIS 160652 (M.D. Pa. Dec. 1, 2015)
The United States Army Corps of Engineers (the “Owner”) entered into a contract (the “Contract”) with Mar-Paul Company, Inc. (“Mar-Paul”) for $3,381,000.00, under which Mar-Paul would serve as general contractor on a construction project for renovations to a building at the Tobyhanna Army Depot in Tobyhanna, Pennsylvania (the “Project”). In turn, Mar-Paul entered into a subcontract (the “Subcontract”) with Butch-Kavitz, Inc. (“Butch-Kavitz”) for $452,000.00, under which Butch-Kavitz would perform the electrical and generator work in connection with the Project.
U.S. District Court for Northern District of California Holds Engineer May Be Liable to Contractor for Breach of Professional Duty and Negligent Misrepresentation
Apex Directional Drilling, LLC v. SHN Consulting Eng’rs & Geologists, Inc., 2015 U.S. Dist. LEXIS 105537 (N.D. Cal. Aug. 11, 2015)
The United States District Court for the Northern District of California held that an engineer that prepares plans and specifications to be relied upon by contractors in preparing their bids for a construction project owes a duty of care to those contractors, and therefore can be held liable to the contractors for breach of professional duty and/or negligent misrepresentation.
Superior Court of Pennsylvania Strictly Construes Procedural Requirements Under Pennsylvania’s Mechanics’ Lien Law
Oakdale Equip. Corp. v. Meadows Landing Assocs., LP, 2015 Pa. Super. Unpub. LEXIS 2067 (Pa. Super. Ct. July 8, 2015)
Meadows Landing Associates, LP (“MLA”) contracted with Richard Lawson Excavating, Inc. (“Lawson”) for work on MLA’s 200-acre subdivision, including earthwork, grading, excavating and pond construction. Lawson then contracted with Oakdale Equipment Corporation (“Oakdale”) to rent heavy equipment for the work. More than one year later, MLA terminated Lawson for failure to achieve substantial completion on time. Oakdale and Lawson both filed mechanics’ lien claims against MLA.
A Case to Watch: Highway Contractor Appeals $663M False Claims Act Judgment
On August 31, 2015, highway contractors Trinity Industries, Inc. and Trinity Highway Products, LLC (collectively, Trinity) appealed to the U.S. Court of Appeals for the Fifth Circuit a $663,360,750 final judgment entered against them under the federal False Claims Act (FCA). At the conclusion of a six-day trial that commenced on October 13, 2014, the jury rendered a unanimous verdict, finding Trinity “knowingly made, used, or caused to be made or used, a false record of statement material to a false or fraudulent claim” in violation of the FCA. The jury unanimously found that the U.S. government suffered damages in the amount of $175,000,000 as the result of Trinity’s FCA violations.