Winger Contr. Co. v. Cargill, Inc., No. 17-1169, 2019 BL 132092 (Iowa Apr. 12, 2019).

On April 12, 2019, the Iowa Supreme Court affirmed a lower court ruling which held that, inter alia, the Iowa mechanic’s lien statute would not permit the attachment of mechanic’s liens to the property of a lessor in connection with a contract to supply materials and labor to a lessee.

Aquatherm, LLC v. CentiMark Corp, 2019 BL 13240 (D. Utah Apr. 12, 2019)

Stag II Lindon LLC and Stag Industrial Inc. (collectively “Stag”) owned a building in Lindon, Utah.  Stag contracted with CentiMark Corp. (“CentiMark”) to perform work on the building’s roof.  CentiMark’s work required it to manipulate, move, and reinstall existing heating cables on the roof.  Shortly after completion of the work, in March of 2014, a fire occurred on the roof which was traced to the location of heat tape, which CentiMark had removed and replaced.