Nova Group/Tutor-Saliba v. United States, 125 Fed. Cl. 469 (Fed. Cl. Mar 16, 2016)

The United States Naval Facilities Engineering Command (the “Navy”) contracted with the joint venture of Nova Group and Tutor-Saliva (the “JV”) for construction of a pier at the Puget Sound Navy Shipyard in Bremerton, Washington.  The contract assigned selection of pier stability assessment methods to the JV’s discretion.  Exercising that discretion, the JV selected a SAP 2000 model for performance design loads.  Five months after the Navy had approved the JV’s design submittals, the Navy’s construction manager voiced concerns about the design and questioned the JV’s reliance upon the SAP 2000 model.

John Spearly Constr., Inc. v. Penns Valley Area Sch. Dist., 2015 Pa. Commw. LEXIS 337 (Pa. Commw. Ct. July 24, 2015)

This action arose out of the construction of a biomass boiler system for the Penns Valley Area School Districts (“District”) to house the District’s boiler plant  (“Project”).  The District contracted with general contractor John Spearly Construction, Inc. (“Contractor”) to construct the Project. The District entered into direct contracts with the Project Architect and other contractors responsible for other components of the work.

Construction began in July 2010 and was to be substantially completed no later than October 18, 2010.  From its inception, however, the Project was plagued with delays.  Project delays were caused by, among other things, delays by the District’s Architect in deciding on and responding to submittals relating to changes, disputes between the District and its HVAC contractor responsible for delivering the boiler, and work performed by a sewer contractor the District brought in toward the end of the Project to repair and replace storm water and sewer pipes. Ultimately, the Project was not substantially completed until August 11, 2011.

Curtiss-Manes-Schulte, Inc. v. Safeco Insurance Company, 2015 U.S. Dist. LEXIS 10032 (W.D. Mo. 2015)

NOTE:  THIS DECISION WAS VACATED ON REHEARING AND THE DECISION ON REHEARING WILL BE THE SUBJECT OF A POST TO BE PRESENTED SHORTLY IN CONSTRUCTLAW.

This dispute between a general contractor and its subcontractor’s performance bond surety arose out of a renovation project at Fort Leonard Wood in Missouri.  On October 19, 2010, the general contractor, Curtiss-Manes-Schulte, Inc. (“CMS”), entered into a subcontract with Balkenbush Mechanical, Inc. to replace the air conditioning system on the project.  A week later, Balkenbush obtained the required performance bond from Safeco Insurance Company of American.

By October 2011, CMS knew that Balkenbush was behind schedule.  In July 2012, CMS responded to a Contract Bond Status Inquiry and informed Safeco that the contract was not complete, that Balkenbush’s work was not progressing satisfactorily, that the project was nine months late, and that liquidated damages would be assessed.  Around the same time, Safeco hired consultants and a law firm to investigate, defend and resolve claims made against four performance bonds Safeco issued to Balkenbush on other projects.  In December 2012, Safeco filed a lawsuit against Balkenbush to recover its losses resulting from the claims on the four other performance bonds.  One month later, in January 2013, Balkenbush filed a bankruptcy petition and Safeco’s counsel entered their appearance in that proceeding.

U.W. Marx, Inc. v. Koko Contracting, Inc., No. 518611, 2015 N.Y. App. Div. LEXIS 600 (N.Y. App. Div. Jan. 22, 2015)

The Appellate Division of the Supreme Court of New York affirmed judgment in favor of a subcontractor holding that although the subcontractor failed to comply with a contractual provision requiring it to give timely notice of its intent to stop work due to contractor’s failure to make payment, the contractor’s prior failure to make three consecutive progress payments to subcontractor constituted an uncured, material breach that relieved the subcontractor from performing its remaining obligations under the parties’ contract.

Milton Reg’l Sewer Auth. v. Travelers Casualty & Surety Co., 2014 U.S. Dist. LEXIS 155419 (M.D. Pa. Nov. 3, 2014)

The United States District Court for the Middle District of Pennsylvania ruled that multiple instances of incomplete and/or defective performance by a contractor did not amount to a material breach so as to excuse the owner from providing notice and an opportunity to cure prior to termination.

United States ex rel JEMS Fabrication, Inc. v. Fidelity & Deposit Co. of Maryland, 2014 U.S. App. Lexis 8175 (5th Cir., April 30, 2014)

This dispute arises out of a construction project to renovate and redevelop pumping stations located at various sites along the Mississippi River.  The U.S. Corp of Engineers entered into a contract with Benetech, LLC for the project.  Benetech then entered into a subcontract with plaintiff JEMS, whereby JEMS agreed to supply custom-fabricated structural steel for use on the project.  The contract amount, including approved change orders, was $2.38 million and required JEMS to provide shop drawings, materials and on-site labor.

JEMS delivered all of the shop drawings and most of the materials required by the subcontract.  However, JEMS did not supply most of the on-site labor, as Benetech and JEMS agreed that Benetech would supply the labor to satisfy its self-performance obligations in its contract with the Corp of Engineers.  JEMS and Benetech also agreed to a subcontract modification such that Benetech would purchase a custom building directly from JEMS’ subcontractor for $54,000.  However, because of changes made by the Corp of Engineers, which were not incorporated into the subcontract, Benetech’s cost for the custom building was $147,000.  Ultimately, Benetech paid JEMS just under $1 million for its work on the project and alleged that JEMS was not entitled to any additional payment.  Benetech claimed that it was entitled to a set-off against any amount due under the subcontract because it had to purchase materials that JEMS should have supplied for the project.