United States Army Corps of Engineers v. John C. Grimberg Co., Inc., No. 2019-1608, 2020 BL 215269 (Fed. Cir. June 9, 2020)

The Court of Appeals for the Federal Circuit reversed a decision by the Armed Services Board of Contract Appeals (“Board”), which had found in favor of a contractor on a Type I differing site condition claim. The Board had held that, even though the contractor’s interpretation of the contract documents was unreasonable, it was more reasonable than the government’s. The Federal Circuit reversed, holding, as a matter of law, that the contractor’s unreasonable interpretation of the contract documents barred its claim.

United States v. John C. Grimberg Co., Case No. 1:16-cv-991, 2017 U.S. Dist. LEXIS 173362 (E.D. Virginia, October 19, 2017)

John C. Grimberg (“Prime Contractor”) was awarded a contract (the “Prime Contract”) to design and complete certain improvements at the FBI Academy in Quantico, Virginia (the “Project”).  Hartford Accident and Indemnity Company (“Surety”) issued payment and performance bonds for the Project pursuant to the Miller Act.  The Prime Contractor thereafter entered into a subcontract (the “Subcontract”) with Kitchens-to-Go (“Subcontractor”) to furnish, install, lease and remove a temporary kitchen facility for the Project.  The Subcontract contained a “no-damages-for-delay” clause, which provided that the Prime Contractor shall not be liable for delays beyond its control and that the Subcontractor is “entitled only to reimbursement for damages for delay actually recovered from the Owner.”  The Subcontract also incorporated the dispute resolution procedures in the Prime Contract, which required that all “disputes arising out of Owner acts, omissions or responsibilities” be submitted through an administrative process with the government’s contracting officer under 41 U.S.C. §§7101 et. seq.

The Subcontract originally contemplated a Project duration of approximately 13 months, ending on April 5, 2014, but was ultimately extended until June 27, 2015.  The Subcontractor submitted its Application for Payment to the Prime Contractor, which included $607,221 for extended rental of the kitchen facilities.  Although the Prime Contractor submitted a payment request to US Department of the Navy (“Owner”), for the extended rental and use of Subcontractor’s temporary kitchen facilities, this request was rejected by the Owner.  The Prime Contractor refused to pay Subcontractor’s Application for Payment and the Subcontractor filed a complaint against the Surety under the Miller Act.