Universal Underwriters Insurance Co. v. A. Richard Kacin, Inc.
916 A.2d 686 (Pa. Super. Ct. 2007)
The Superior Court of Pennsylvania held that the American Institute of Architects’ (“AIA”) form waiver of subrogation clause barred a subrogation claim even where the loss was created by the contractor’s own negligence. Relying on Penn Avenue Place Assoc., L.P. v. Century Steel Erectors, Inc., 798 A.2d 256 (Pa. Super. Ct. 2002), the court held that a warranty provision did not invalidate the waiver of subrogation and opined that the warranty provision provided a remedy only to the extent that losses were not covered by insurance. The court further held that an insurer does not need to be party to the contract containing the waiver of subrogation clause nor does the insurer need to consent to or have notice of the waiver of subrogation clause in order for it to be enforceable.
general contractor
Contractor’s Negligent Supervision Claims Against Construction Manager Require Privity, But Negligent Representation Claims Do Not
Dynalectric Co. v. Whittenberg Constr. Co.
2007 U.S. Dist. LEXIS 27025 (W.D. Ky. Apr. 10, 2007)
Defendant project-owner Luther F. Carson Four Rivers Center, Inc. contracted with Whittenberg Construction Company to serve as general contractor in the construction of a fine arts facility and with defendant Ray Black & Son, Inc. to serve as construction manager. Whittenberg contracted the electrical contracting work to Plaintiff Dynalectric. Dynalectric brought suit against Four Rivers and Black, alleging that they had caused its work to take longer and cost more than anticipated and as a result Dynalectric had not been fully compensated for its work on the project.
General Contractor Unable to Enforce Subcontract Bid Which Disclaimed Intent to Be Bound
Fletcher-Harlee Corp. v. Pote Concrete Contractors, Inc.
2007 U.S. App. LEXIS 7808 (3d Cir., Apr. 5, 2007 )
The United States Court of Appeals for the Third Circuit held that, despite the commercial practice to the contrary, a subcontractor was not bound by the qualified bid it submitted to a general contractor. The subcontractor’s bid plainly stated that the price was for information purposes only and should not be relied on by the recipient.
General Contractor Fletcher-Harlee solicited subcontract bids for concrete work. As is an industry custom, Fletcher-Harlee stated in its solicitation letter that bids must be held open for a minimum of 60 days and also that the subcontractor must agree to be accountable for the prices and proposals submitted. Pote Concrete Contractors submitted a written bid. However, Pote included a disclaimer in its submission. In the bid, Pote stated that the price quote was for informational purposes only, was not a firm offer, should not be relied on and that Pote did not agree to be held liable for any of the terms that it submitted.
Owner’s Failure To Preserve Evidence Justified Dismissal Of Claims For Defect As Sanction For Spoliation Of Evidence
Harborview Office Ctr., LLC v. Camosy Inc.
2006 Wisc. App. LEXIS 149 (Wis. Ct. App. Feb. 15, 2006)
Project owner Harborview entered into a contract for the construction of a three-story office building. After discovering significant water infiltration problems, Harborview filed suit against the parties who had provided services in its construction: the general contractor, the architectural firm, the installer of aluminum windows, and the installer of the Exterior Insulation and Finishing System (EIFS). Harborview alleged negligence and breach of contract against each and claimed that in order to resolve the water infiltration problem it would be necessary to remove and replace all of the building’s windows. Harborview hired an expert, who was an architect and engineer, to identify the causes of the problem, evaluate a correction process, and ultimately oversee the remediation process.
Construction Manager Sued For Failure To Ensure Quality Of Contractor’s Work Could Not Sue Contractor’s Surety For Indemnity Or Contribution
Carolina Casualty Insurance Company, et al. v. R.L. Brown & Associates, Inc., et al.
No. 1:04-CV-3537-GET, 2006 U.S. Dist. LEXIS 5261 (N.D. Ga. January 25, 2006)
In Carolina Casualty Insurance Company, et al. v. R.L. Brown & Associates, Inc., et al., No. 1:04-CV-3537-GET, 2006 U.S. Dist. LEXIS 5261 (N.D. Ga. January 25, 2006), a dispute arose between a surety that had provided a performance bond on a public works project and the project’s program manager. After the owner declared the general contractor in default for defective work, the surety finished the underlying contract under the terms of the performance bond. The owner sought additional damages from the surety. In an agreement settling those claims for additional damages, the owner assigned to the surety all of its own claims against third parties arising out of the defective construction and supervision of the project.
Terms Of Subcontract Containing A “Pay-If-Paid” Clause Enforceable Under Both Texas And New Mexico Law
MidAmerica Construction Management, Inc. v. MasTec North America, Inc., et al.
2006 U.S. App. Lexis 3022 (10th Cir. 2006)
In MidAmerica Construction Management, Inc. v. MasTec North America, Inc., et al., 2006 U.S. App. Lexis 3022 (10th Cir. 2006), the Court held that a subcontract agreement contained a “pay-if-paid” clause, and that the clause in question was enforceable under both Texas and New Mexico law. As a result, general contractors did not need to pay the subcontractor for the work that the subcontractor performed under the contract, because the general contractors had not been paid by the project owner for that work.
Contractor’s Continued Acceptance of Subcontractor’s Performance Waives Right To Terminate
Ed Kimber Heating & Cooling, Inc. v. Travelers Casualty & Surety Co.
No. 3:03cv2111 (SRU), 2006 U.S. Dist. LEXIS 3323 (D. Conn. Jan. 26, 2006)
Trataros Construction, Inc. (“Trataros”), the general contractor on a school addition and renovation project, subcontracted with Ed Kimber Heating & Cooling, Inc. (“Kimber”) for the performance of HVAC and plumbing work. Travelers Casualty & Surety Co. (“Travelers”) issued payment and performance bonds as the surety for Trataros.
Payment Bond Does Not Cover Major Repairs to Heavy Construction Equipment Akin to Capital Improvements
Beckwith Machinery Company v. Asset Recovery Group, Inc.
2005 Pa. Super. 429, 2005 Pa. Super. LEXIS 4276 (Pa. Super. Ct. 2005)
In Beckwith Machinery Company v. Asset Recovery Group, Inc., et al., 2005 Pa. Super. 429 (Pa. Super. Ct. 2005), the Court held that invoices for major repairs in the nature of capital improvements to heavy construction equipment were not covered by the terms of a payment bond. The Court reasoned that the repairs referenced in the invoices at issue could not be classified as ordinary maintenance performed for consumption over the course of the project, but rather were services which a contractor would retain the benefit of on the completion of work to be used by him in a like manner on subsequent projects.
Acceptance of Subcontractor’s Work by General Contractor Relieves the Subcontractor of Liability to Employee of Following Subcontractor
Webber v. McBride & Sons Contracting Co.
No. ED86076, 2005 Mo. App. LEXIS 1846 (Mo. Ct. App. Dec. 13, 2005)
A painter suffered personal injuries after falling through a stairwell hole in the floor of an unfinished single-family residence. The stairwell hole had been cut by predecessor subcontractors no longer on the site. At the time of the fall, the general contractor, which also owned the residence, had already accepted the work of the subcontractors as completed.
Missouri Court Holds Subcontractor Tortiously Interfered with Contractor’s Agreement with Owner by Seeking Payment Directly from Owner
Environmental Energy Partners Inc. v. Siemens Building Technologies,Inc., et al.
Nos. 26521 & 26702, 2005 Mo. App. LEXIS 1568 (Mo. Ct. App., Oct. 25, 2005)
In Environmental Energy Partners Inc. v. Siemens Building Technologies, Inc., et al., Nos. 26521 & 26702, 2005 Mo. App. LEXIS 1568, a payment dispute arose between a contractor and its subcontractor on a hospital renovation project. When the contractor refused to pay the subcontractor the remaining subcontract balance ($201,178.75) on the basis that the subcontractor’s work was not completed, the subcontractor filed a mechanic’s lien against the property. The subcontractor then filed a petition to enforce its lien, naming the contractor and owner as defendants. Because of the subcontractor’s lien, the owner withheld the last installment payment of $148,475 due to the contractor under their agreement. Thereafter, and unbeknownst to the contractor, the subcontractor and the owner entered into a confidential “Settlement Agreement and Release” under which the owner agreed to pay directly to the subcontractor the $148,475 amount that it was withholding from the general contractor in exchange for a release of the lien upon entry of judgment in the litigation.