Aquatherm, LLC v. CentiMark Corp, 2019 BL 13240 (D. Utah Apr. 12, 2019)

Stag II Lindon LLC and Stag Industrial Inc. (collectively “Stag”) owned a building in Lindon, Utah.  Stag contracted with CentiMark Corp. (“CentiMark”) to perform work on the building’s roof.  CentiMark’s work required it to manipulate, move, and reinstall existing heating cables on the roof.  Shortly after completion of the work, in March of 2014, a fire occurred on the roof which was traced to the location of heat tape, which CentiMark had removed and replaced.Continue Reading District Court in Utah Grants Summary Judgment for Contractor Against Insurance Subrogation Claim Based on Contractual Waiver Provision and Statute of Limitations

Arco Ingenierosm, S.A. v. CDM Int’l Inc., Civil Action No. 18-12348-PBS, 2019 BL 100779 (D. Mass. Mar. 22, 2019)

In November 2009, Tropical Storm Ida hit El Salvador, causing flooding, landslides, and the destruction of homes, roads, bridges, schools, health clinics, and other infrastructure.  The United States Agency for International Development (“USAID”) provided $25 million in funding to rebuild damaged infrastructure.  USAID retained Defendant CDM International Inc. (“CDM”) to conduct studies and assessment for the construction of eight schools and one health clinic (the “Projects”) and to create preliminary designs and technical specifications for these Projects.  These preliminary designs were intended to constitute at least thirty percent of final designs for the Projects.  Relying on the preliminary designs created by CDM, Plaintiff Arco Ingenieros, S.A. de C.V. (“ARCO”) submitted bids to act as the design-build contractor for the Projects.  USAID awarded the Projects to ARCO.Continue Reading Contractor’s Third Party Beneficiary Claim Dismissed Against Designer Where Designer’s Contract with Owner Lacked Clear Intent to Benefit the Contractor

Whiting-Turner Contracting Co. v Guar. Co. of N. Am. USA, 2019 BL 97923 (Colo. App. Mar. 21, 2019).

This construction dispute involved rights and obligations under a performance bond supplied for an office building construction project in Denver, Colorado.  Whiting-Turner Contracting Company was the general contractor, and it subcontracted Klempco Construction to construct an anchor system for the project’s underground parking garage.  Klempco provided performance and payment bonds for the project from Guarantee Company of North America USA (“GCNA”).  When Klempco fell behind schedule, it stopped paying its sub-subcontractors and directed Whiting-Turner to assume responsibility for its work and sub-subcontractors.Continue Reading Colorado Court of Appeals Finds Contractor Satisfied Conditions Precedent Under Performance Bond

Team Contractors, LLC v. Waypoint Nola, LLC, No. 16-1131, 2019 BL 96133 (E.D. La. Mar. 20, 2019)

The Eastern District of Louisiana recently denied the motion of a prime contractor (the “Contractor”) for summary judgment on its breach of contract claim against the owner (the “Owner”) of a construction project in New Orleans (the “Project”) where the primary issue involved whether a suspensive condition was enforceable.Continue Reading Federal Court in Louisiana Upholds Suspensive Condition Not Subject Solely to Owner’s Whim

SMJ Gen. Constr., Inc. v. Jet Commer. Constr., LLC, No. S-16785/16985, 2019 BL 131640 (Alaska Apr. 12, 2019)

In 2016, Jet Commercial Construction, LLC (“Jet”) entered into a subcontract with SMJ General Construction, Inc. (“SMJ”) to supply materials and labor for the construction of a restaurant in Hawaii.  The subcontract contained a dispute resolution provision that required the parties to first mediate any dispute and then submit it to arbitration if mediation was unsuccessful.  It also included a choice-of-law and venue provision designating Oklahoma Law and the courts of Cleveland County, Oklahoma for any lawsuits pertaining to the Agreement’s enforcement.Continue Reading Alaska’s Supreme Court Holds That Executing a Settlement Agreement Releases Parties from Contractual Obligation to Arbitrate Disputes

R&O Constr. Co. v. MBA Gen. Contracting, LLC, No. 1:18-cv-00042, 2019 BL 98680 (D. Utah Mar. 21, 2019)

On March 21, 2019, a Utah federal court granted Defendants MBA General Contracting, LLC and Cory Martin’s motion to dismiss R&O Construction Company’s claim for attorney fees.
R&O, as general contractor of a construction project, entered into two subcontracts with MBA to perform concrete work.  The first subcontract, entitled Master Subcontract Agreement, outlined general obligations between the parties.  The second, entitled Work Authorization Document, outlined more specific obligations.  R&O asserted various causes of action against MBA arising from MBA’s alleged breach of the subcontracts, including a claim for attorney fees.  MBA moved to dismiss the attorney fees claim, arguing that neither subcontract provides for such an award.Continue Reading Utah Federal Court Dismisses Claim for Attorney Fees Finding That Neither the Indemnification Provision nor the Failure-To-Perform Provision Applies to a Lawsuit Between Contractor and Subcontractor