Kit-San-Azusa v. United States,
1996 U.S. App. LEXIS 10370 (Fed. Cir. Ct. App., May 7, 1996).
Government contractor’s differing site conditions claim based on the discovery of unanticipated boulders during excavation was upheld even though the Government’s general description of the site stated that cobbles and boulders were present at

Roy A. Elam Masonry, Inc. v. Fru-Con Construction Corporation,
1996 Mo. App. LEXIS 481 (March 26, 1996).
On November 14, 1988, the general contractor, Fru-Con Construction Corp. (Fru-Con) entered into a construction contract with Southwestern Redevelopment Corp (SRC), the owner. In early 1989, Fru-Con and a subcontractor Roy A. Elam

State of Florida, Department of Insurance v. The United States,
81 F.3d 1093 (U.S. App. 1996) LEXIS (Fed. Cir. 1996).
The construction contract at issue in this case resulted in a default termination of the contractor and the contractor’s surety. The surety’s receiver sued the United States for damages based

Hazleton Area School District v. Bosak,
671 A.2d 277 (Pa. Cmwlth. 1996).
In this case, neither of the arbitration provisions provided in the 1988 and 1989 agreements specifically stated that an action in tort for negligence should be arbitrated. The Commonwealth Court affirmed the decision of the trial court and

J.P. Altmayer v. R.W. Johnson,
79 F.3d 1129 (Fed. Cir. 1996).
GSA had planned to order the carpet and trim for the office by August 1992 but did not do so despite repeated requests from Altmayer who tried to impress the importance of this for the contract to be completed

Lahr Construction Corp. (doing business as LeCesse Construction Co.) v. J. Kozel & Son, Inc.,
640 N.Y.S.2d 957 (Misc 1996).
This is an action brought by a general contractor against a subcontractor for damages where the subcontractor moved for summary judgment saying that the general contractor could not recover damages

Pavel Enterprises, Inc. v. A.S. Johnson Company, Inc.,
342 Md. 143; 674 A.2d 521; (1996)
The National Institutes of Health (NIH) solicited bids for a renovation project. Pavel Enterprises Incorporated (PEI), a general contractor, prepared a bid for the NIH work. In preparing its bid, PEI solicited sub-bids from various mechanical subcontractors. The A.S. Johnson Company (Johnson), a mechanical subcontractor, responded with a written scope of work proposal on July 27, 1993, giving a verbally submitted bid price on the morning of August 5, 1993, the day NIH opened the general contractors’ bids. Neither party disputes that PEI used Johnson’s sub-bid in computing its own bid.

Danis Clarkco Landfill Co. v. Clark County Solid Waste Mgmt. Dist.,
653 N.E.2d 646, 73 Ohio St.3d 590, 1995 Ohio LEXIS 1869 (Ohio, September 6, 1995).
County solid waste management district was not subject to provisions of public bidding law in making “designation” of exclusive provider of solid waste management services, but was required only to adhere to bidding procedures it set for itself in its RFP. 
Danis Clarkco Landfill Company (“Danis”), a landfill operator, filed an action seeking declaratory and injunctive relief to prevent a county solid waste management district (the “District”) from designating a rival bidder as the sole provider of waste management services for the District. The District had prepared a Request for Proposal (“RFP”) seeking “proposals from qualified bidders to design, construct and operate solid waste management facilities” for the District.

West-Fair Elec. Contractors v. Aetna Casualty & Surety Co.,
78 F.3d 61, 1996 U.S. App. LEXIS 3912 (2d Cir. March 6, 1996).
Neither general contractor nor surety could assert pay-when-paid clause as defense to payment claim by subcontractor because clause, which operated as a condition precedent to payment, constituted a prospective waiver of lien rights and therefore violated New York Lien Law. 
Defendant Gilbane Construction Co. (“General Contractor”) was the general contractor on a construction project in White Plains, NY. General Contractor hired plaintiff L.J. Coppola, Inc. (“Subcontractor”) to perform a portion of the work. General Contractor maintained a payment bond with defendant Aetna Casualty and Surety Co. (“Surety”) for the benefit of all its subcontractors.

H. Verby Co., Inc. v. United States Fire Ins. Co.,
1996 E.S. Dist. LEXIS 3056 (March 13, 1996) (U.S.D.C., S.D.N.Y.).
A material supplier was entitled to recover on the general contractor’s payment bond even though it had received an assignment of two debts from general contractor; supplier had not made an “election of remedies” in accepting the assignment and there was no evidence that the contractor’s assignment discharged the underlying debt upon which the supplier sued the surety.
H. Verby Co., Inc. (“Supplier”) contracted with a Contractor to supply roofing waterproofing and insulations materials for a school roof replacement project. The Defendant, United States Fire Ins. Co. (“Surety”) and the Contractor executed a labor and material payment bond in favor of the Owner. After the Contractor refused the Supplier’s demands for payments, the Supplier brought the present action against the Surety for $61,068.44, the amount of the outstanding balance due.