McKinney & Moore, Inc. v. City of Longview, Texas
2009 Tex. App. LEXIS 9299 (Tex. App., Dec. 8, 2009)

The Court of Appeals of Texas for the Fourteenth District held that a general contractor’s acceptance of final payment barred its claims for compensation for extras. The Court relied on the express release language in the parties’ contract to support its ruling.

The City of Longview, Texas (the “Owner”) retained McKinney & Moore, Inc. (“MMI”) to serve as a general contractor for the construction of the Lake O’ the Pines Raw Water Intake Structure (the “Project”). The parties’ contract contained various provisions related to subsurface conditions and the Owner supplied reports regarding such conditions. Among other things, the contract also provided that the Owner was responsible for design accuracy and sufficiency of the contract documents. The contract further addressed circumstances under which MMI would be entitled to reimbursement for damages and the effect of MMI’s acceptance of final payment.

Excavation Technologies, Inc. v. Columbia Gas Co. of PA
2009 Pa. LEXIS 2794 (Pa., December 29, 2009)

The Pennsylvania Supreme Court held that a utility company’s failure to properly mark the location of its lines under the Pennsylvania One-Call Act did not render it liable to an excavation contractor who struck the lines and suffered purely economic losses. It rejected the argument that the utility should be liable under § 552(3) of the Restatement (Second) of Torts because of its public duty to mark the lines.

Federal Insurance Co. v. Philotimo, Inc.
2009 U.S. Dist. Lexis 108105 (W.D.P.A. Nov. 19, 2009)

Homeowner hired defendant to inspect and clean its fireplace and chimney after observing chunks of mortar falling into the fireplace. Homeowner showed defendant’s technicians the fallen mortar. The technicians cleaned and visually inspected the chimney and reported to homeowner that it “looked good.” Thereafter, an extensive fire swept through the house causing over $400,000 in damage.
Following the fire, homeowner’s insurer commissioned an inspection which revealed numerous signs of damage and disrepair to the chimney that suggested defendant’s technicians should have instructed homeowner not to use fireplace and chimney until repairs were made.

Life Receivables Trust v. Syndicate 102 at Lloyd’s of London
2008 U.S. App. LEXIS 24977 (Nov. 25, 2008)

The Second Circuit held that section 7 of the Federal Arbitration Act (“FAA”) does not permit an arbitrator to compel pre-hearing document discovery from non-parties to the arbitration. However, the court noted that a non party could be subpoenaed to produce documents at a preliminary hearing on non-merits issues before one or more arbitrators.

Kiski Area Sch. Dist. v. Mid-State Surety Corp.
2008 Pa. LEXIS 2260 (Dec. 17, 1988)

Kiski Area School District (“the District”) entered into an agreement with contractor, Lanmark, for the construction and renovation of an elementary school. Mid-State Surety Corporation (“Midstate”) provided a performance bond for the project naming Lanmark as principal and the District as obligee.

The District became dissatisfied with the quality and timeliness of Lanmark’s work, declared it in default, withheld final payment and demanded that Mid-State assume responsibility for the remaining work. The District did not remit the remaining contract balance to Mid-State. Lanmark filed suit against the District seeking payment of the contract balance (the “Lanmark Matter”). The District counterclaimed and joined Mid-State. The District also filed a separate action against Lanmark and Mid-State (“the District Matter”), which was stayed pending resolution of the Lanmark Matter.

Hunt Construction Group, Inc. v. Brennan Beer Gorman / Architects, P.C.
2008 U.S. Dist. LEXIS 93754 (D. Vt. 2008)

In declining to apply an exception to the economic loss rule, the Court dismissed a contractor’s negligence claims against the project architect (and other design professionals).

In 2005, Spruce Peak Realty, LLC (“Owner”), retained Plaintiff, Hunt Construction Group (“Contractor”), to construct a resort hotel in Stowe, Vermont. Owner and Contractor executed a contract setting forth their respective rights and responsibilities on the Project. Owner then contracted with an architect, mechanical, electrical and plumbing engineers, a structural engineer, and an interior designer (collectively, the “Design Professional Defendants”). Contractor was to build the Project according to the plans and specifications the Design Professional Defendants provided under contracts with Owner.

Atlantic City Associates LLC v. Carter & Burgess Consultants, Inc.
2008 U.S. Dist. LEXIS 93684 (D.N.J. Nov. 13, 2008)

The United States District Court for the District of New Jersey was asked to resolve the effect of liability limiting provisions on an architect’s indemnity obligations to an owner under a professional services agreement. Determining that the consequential damages provision and the indemnification provision contained in the agreement could be harmonized, the Court held that the architect would only be liable for indemnification of direct, and not consequential, damages. The Court held, however, that a damages cap contained in the architect’s proposal, which was made a part of the contract by incorporation, could not be harmonized with the indemnity clause, so that under the contract, the indemnity provision took precedence over the damages cap.

Steadfast Insurance Co v. Brodie Contractors, Inc.
2008 U.S. Dist. LEXIS 88448 (October 31, 2008 W.D. Va.)
Steadfast Insurance Co., as subrogee of Skanska USA Building Co., the general contractor, alleged claims for breach of contract and breach of warranty against Brodie Contractors, Inc., a masonry subcontractor, concerning replacement of brick veneer on the Danville Regional Medical Center. Brodie moved for summary judgment alleging that the lawsuit was barred by Virginia’s statute of limitations.

City of Gillette v. Hladky Construction, Inc.
2008 Wyo. LEXIS 139 (November 14, 2008)
The Supreme Court of Wyoming upheld an award to a Contractor of more than one million dollars against an Owner for a breach of an implied covenant of good faith and fair dealing even though the Owner did not breach the contract’s express terms.
The City of Gillette (“City”) hired Hladky Construction, Inc. (“HCI”) for the remodel and expansion of City Hall. The project specifications called for the installation of precast concrete exterior panels that matched those on the existing structure. Further, there was a requirement that the plant at which the precast panels were to be manufactured be certified under the Precast/Prestressed Concrete Institute Plant Certificate Program prior to the start of their production. HCI submitted a bid that unknown to it named an precast manufacturer which had not yet received the required certification. Both the City hired architect and structural engineer were aware prior to bid acceptance that HCI’s precast manufacturer was in the process of obtaining certification, but was not yet certified. Despite knowing that HCI’s manufacturer was not certified and a contract provision requiring the architect to notify bidders of any bid objections, no City representative objected or informed HCI about its uncertified precast manufacturer.

Somerset Village Townhomes Condominium Owners’ Association v. Allied Construction, Inc.
2008 Wash App. LEXIS 2178 (September 2, 2008)
Developer, Far Northwest Development Co, LLC (“Far Northwest”) contracted with Steinvall Construction (“Steinvall”) for the construction of the Somerset Village Townhomes. The contract between Far Northwest and Steinvall stated that “[t]he Contract Documents shall not be construed to create a contractual relationship of any kind . . . between the Owner and a Subcontractor . . .” Steinvall subcontracted portions of its work. The subcontracts incorporated the general conditions of the Far Northwest –Steinvall contract and also imposed certain obligations on the subcontractors concerning Far Northwest, including, inter alia, obtaining insurance to protect its interests and indemnifying Far Northwest for certain claims.