Nova Crete, Inc. v. City of Elizabeth
2010 N.J. Super. Unpub. LEXIS 101 (N.J. Super. Ct. App. Div. Jan. 15, 2010)

The Court held that the consent of surety submitted by Nova Crete, Inc. (“Nova Crete”) did not comply with the bid specifications provided by the City of Elizabeth because its issuance was conditioned on an event other than the award of the contract to Nova Crete, and it therefore did not comply with the applicable New Jersey statute. Furthermore, this defect was material and could not be waived or cured. As a result, Elizabeth properly determined that Nova Crete was not the lowest responsible bidder on the project.

American Manufacturers Mutual Insurance Co. v. Payton Lane Nursing Home, Inc.
2010 U.S. Dist. LEXIS 8537 (E.D.N.Y. Feb. 2, 2010)

The United States District Court for the Eastern District of New York (“EDNY”) recently considered whether a surety could maintain a breach of contract claim against a construction project owner’s architect based upon the architect’s alleged wrongful certification of payments occurring prior to the execution of a takeover agreement. In rendering its opinion, the EDNY concluded that expert opinions were not required where the claim sounded in contract, rather than in tort. The EDNY also found that summary judgment was defeated because there remained genuine issues of material fact as to the extent of the architect’s scope of construction phase services and whether the architect failed to satisfy its construction phase service obligations.

Bell BCI Co. v. United States
570 F.3d 1337 (Fed. Cir. Jun. 25, 2009)

Plaintiff, Bell BCI Company (Bell), a general contractor, sued the United States (the “Government”) for damages plus interest under the Contract Disputes Act for the unpaid balance of the contract price, unresolved change order claims, delay damages, labor inefficiency costs and profit thereon. Bell also asserted claims on behalf of five subcontractors.

Addicks Services, Inc., Appellant v. GGP-Bridgeland, LP
2010 U.S. App. LEXIS 2623 (5th Cir. Feb. 8, 2010)

Plaintiff, Addicks Services, Inc. (“Addicks”) sought damages for extra work and delay costs incurred while performing land improvement work for a residential development in Texas. Addicks’ claims were denied by the district court because Addicks executed monthly waivers and releases to receive progress payments which waived their claims for extra work and delay costs.

Goldsmith Assoc., Inc. v. Del Frisco’s of Philadelphia, Inc.
2009 U.S. Dist. LEXIS 92193 (E.D. Pa. Oct. 1, 2009)

Grasso Holding Acquisition, Inc. (“Grasso”) entered into a lease with Del-Frisco’s of Philadelphia (“Del-Frisco’s”) to occupy and renovate the bottom floors of the Packard Building in Philadelphia, PA for use as a restaurant. Building owners, Chest-Pac Associates, Inc. (“Chest-Pac”) and Grasso, reserved the right to review and approve the designs for the renovation. Once the lease expired, the renovation improvements were to become the sole property of Chest-Pac and Grasso. After negotiating the lease, Del-Frisco’s contracted with Lorient, LLC to serve as the general contractor for the renovations. Lorient then subcontracted with Plaintiff, Goldsmith Associates, Inc. (“Goldsmith”) to provide the electrical work. Goldsmith submitted invoices in the amount of $1,835,110.87 but was allegedly only paid $734,879.30. Goldsmith commenced an action against Del Frisco’s, Chest-Pac and Grasso, asserting a claim of unjust enrichment, and seeking to recover $1,100,231.57 in unpaid work. The defendants moved to dismiss the Complaint as legally insufficient.

Fortney & Weygandt, Inc. v. American Manufacturers Mutual Insurance Co.
2010 U.S. App. Lexis 2836 (6th Cir. Feb. 12, 2010)

The United States Court of Appeals for the Sixth Circuit recently held that where a contractor’s defective foundation work required complete demolition and rebuilding of project that the defective work exclusion of commercial general liability policy did not preclude coverage for destruction of portions of the building not defectively constructed.

A.A. Bellucci Constr. Co. v. United States Surety Co.
2010 U.S. Dist. LEXIS 8369 (M.D. Pa., Feb. 2, 2010)

CSI Engineering, DC, P.C. (“CSI”) entered into a contract with a division of the U.S. Department of Labor to act as the general contractor for one of its construction projects. In turn, CSI subcontracted a portion of the work to A.A. Bellucci (“Bellucci”). The contract between CSI and Bellucci required mediation and arbitration to resolve disputes between them. To secure payment to all of its subcontractors, including Bellucci, CSI furnished Miller Act payment bonds from United States Surety Company (“Surety”) and U.S. Specialty Insurance Company (“Speciality”).

Hunt Construction Group, Inc. v. National Wrecking Corporation
587 F.3d 1119; 2009 U.S. App. LEXIS 25909 (2009)

Plaintiff, Hunt Construction Group (“Hunt”), commenced an action against one of its subcontractors, National Wrecking Corporation (“National”) and against two sureties (the “Sureties”) on National’s performance bond. The Sureties argued that Hunt failed to give timely notice of default depriving the Sureties of a realistic opportunity to exercise their rights under the bond to cure National’s defective performance.

GTECH Corp. v. Commonwealth, Dept. of Revenue
965 A.2d 1276 (Pa. Commw. 2009)

The Commonwealth Court of Pennsylvania considered whether the Pennsylvania Procurement Code provides the exclusive remedy for aggrieved bidders to challenge the procedure and outcome of bidding contests in the context of a procurement for the Pennsylvania Lottery. The Court found that while the Procurement Code provides an exclusive remedy for substantive challenges (i.e., a general right of protest to an offeror who is aggrieved in connection with the solicitation or award of a contract), it did not provide a remedy for procedural challenges.

U.S. for Use and Benefit of Greenmoor, Inc. v. Travelers Casualty and Surety Co.
2009 U.S. Dist. LEXIS 113153 (W.D. PA 12/04/2009)

The Court held that a properly terminated subcontractor was nevertheless entitled to payment for contract work and extras performed prior to termination, less certain offsets for contractor’s damages. Subcontractor was also entitled to interest at 1% per month under a prompt payment statute, but because it was properly terminated was not entitled to lost profit on the terminated portion of the subcontract.