Laquila Grp., Inc. v. Hunt Constr. Grp., Inc., 2014 N.Y. Misc. LEXIS 2824 (N.Y. Sup. Ct. June 25, 2014)
This action arose out of a payment dispute following construction of the Barclays Center in Brooklyn, New York. General contractor Hunt Construction Group, Inc. (“Hunt”) retained Laquila Group, Inc. (“Laquila) as a subcontractor to perform excavation and foundation work for the project. The parties executed a subcontract whereby Laquila would perform the work for $27.5 million with the understanding that the work had to be completed in a timely manner due to events at Barclays already scheduled around the completion date. The subcontract further specified that Hunt was not liable to Laquila for any additional costs or changes in the work absent a written change order.
The project experienced various complications, which resulted in the parties entering into numerous change orders. Hunt paid Laquila the money due under the original $27.5 million subcontract, plus payments covering the change orders. Each change order executed by Laquila contained the clause, “[a]cceptance of this Change Order constitutes a waiver of any claim, additional compensation and time whatsoever in relationship to the items covered under this Change Order.” Moreover, with each progress payment, Laquila submitted releases and a “Partial Waiver of Claims” including a waiver of liens that confirmed that it had been properly paid for its work.