USA Walnut Creek, DST v. Terracon Consultants, Inc. f/k/a HBC Engineering, Inc., 2015 Tex. App. LEXIS 1806 (Tex. App. 2015)

This cases arises out of the construction of a twelve building apartment complex in Austin Texas.  The builders, Creekstone Walnut, LP and Creekstone Builders, Inc., contracted with defendant Terracon for geotechnical engineering and inspection services.  As part of the services, Terracon performed test borings and provided the geotechnical recommendations for, among other things, the foundation design.  Terracon’s inspection services included providing testing and inspection of the construction materials, including compaction testing on the earthwork.

Montano Elec. Contractor v. United States, 2015 U.S. App. LEXIS 5928 (Fed. Cir. Apr. 13, 2015)

The Army Corps of Engineers (“the Corps”) hired a general contractor, who subcontracted certain electrical work to Montano (“Subcontractor”).  When Subcontractor was not paid for its work, Subcontractor sought assistance from the Corps’ contracting officer, who explained that he was unable to assist because Subcontractor did not have a contract with the government and the government was thus not a party to Subcontractor’s dispute; however, Subcontractor should pursue any claims it had against the general contractor in federal district court under the Miller Act.

G.T. Leach Builders, LLC v. Sapphire V.P., 2015 Tex. LEXIS 273 (Tex. Mar. 20, 2015)

This action arose after 2008’s Hurricane Dolly caused extensive damage to a luxury condominium project that Sapphire V.P., L.P. (“Developer”) was in the process of developing on South Padre Island (the “Project”).  In 2009, the Developer sued insurance brokers for negligence and breach of contract, alleging that they let the builder’s risk insurance policy expire eight days before the storm struck and be replaced by a permanent policy even though construction of the Project was not yet complete.  The Developer sought to recover millions of dollars for water damage and other increased building costs it alleged that the builder’s risk policy covered or should have covered but the permanent policy did not.

Fed. Ins. Co. v. Fredericks, Inc., 2015-Ohio-694, 29 N.E.3d 313, 2015 Ohio App. LEXIS 684 (Ohio Ct. App. Feb. 27, 2015)

This case arises from a construction project in Vandalia, Ohio that was damaged during a windstorm before construction was completed.  The project was for the construction of a “cross-dock facility” warehouse (the “Project”) on certain real property owned by Pasco Enterprises (“Pasco”), a company in the business of owning and leasing real estate holdings.  Pasco’s 100% parent, J.P. Holding Co., Inc. (“JP Holding”) also owned Carter Express, Inc. (“Express”) and Carter Logistics, LLC (“Logistics”).  Logistics was in the business of providing freight transportation services to its customers; it also contracted with freight carriers, including Express, to transport its customers’ freight.  Approximately 85% of Logistics’ freight shipments were transported by Express.

NYU Hosps. Ctr. v. HRH Constr. LLC, 2015 U.S. Dist. LEXIS 31967 (S.D.N.Y. Mar. 12, 2015)

NYU Hospitals Center (“NYU”) hired HRH Construction LLC (“HRH”) to renovate NYU’s radiology center. HRH entered into subcontracts with various trades to complete the work. The renovation project was to proceed in several phases, and the contract between NYU and HRH called for HRH to submit monthly payment requisitions for costs and expenses incurred during the preceding month.

Clipper Pipe & Service, Inc. v. The Ohio Cas. Ins. Co., 2015 Pa. LEXIS 1275 (PA  June 15, 2015)

The Supreme Court of Pennsylvania held that CASPA, 73 P.S. §§501-516, “does not apply to a construction project where the owner is a governmental entity.”  The decision once and for all resolved the issue of whether the Contractor and Subcontractor Payment Act (“CASPA”) applies to payment disputes between prime contractors and subcontractors on public works projects,  either instead of, or in addition to, the prompt payment provisions of the Commonwealth Procurement Code, 62 Pa.C.S. §§ 3931-3939 (commonly referred to as “the Prompt Payment Act”).

East Coast Paving & Sealcoating, Inc. v. N. Allegheny Sch. Dist., 111 A.3d 220 (Pa. Commw. Mar. 6, 2015).

North Allegheny School District (“Owner”) hired East Coast Paving & Sealcoating, Inc. (“Contractor”) to pave several large areas.  Shortly after Contractor began its paving work, Owner’s architect found “soft spots” in the areas to be paved.  Contractor’s scope of work under the contract did not include soft spot repair work, in which soft ground is replaced with compacted stone before paving, but Contractor and Owner’s Director of Facilities, who had the authority to authorize additional work, agreed that Contractor would do the repair work.  Owner’s architect’s finding of soft spots and Owner’s Director of Facilities’ agreement with Contractor were documented in a report to Owner.  A second report to Owner documented Contractor’s commencement of the repair work.

State v. Perini Corp., 2015 N.J. LEXIS 388 (N.J. April 30, 2015)

The Supreme Court of New Jersey held that for an improvement supplying critical utilities to multiple buildings constructed as part of a multi-phase construction project, the ten year statute of repose (N.J.S.A. 2A:14-1.1(a)) begins to run from that time when the final buildings comprising the project are substantially complete and the improvement is hooked up to all of the buildings it is designed to serve.

Curtiss-Manes-Schulte, Inc. v. Safeco Insurance Company, 2015 U.S. Dist. LEXIS 57836 (W.D. Mo. May 4, 2015) 

In this opinion, the United States District Court for the Western District of Missouri (i) vacated its earlier order denying the surety’s motion for summary judgment (see earlier post) and (ii) held that the contractor’s failure to formally declare the sub-contractor in default precluded the contractor from recovering from the subcontractor’s performance bond surety.  The dispute involved the contractor, Curtiss-Manes-Shulte, Inc. (“CMS”) and Safeco Insurance Company of America (“Safeco”), who provided a performance bond to Balkenbush, CMS’s mechanical subcontractor.

Marenalley Constr., LLC v. Zurich American Ins. Co. and Nason Constr. Inc., 2015 U.S. Dist. LEXIS 30968 (E.D. Pa. March 13, 2015)

This payment dispute case arises out of a Veterans Affairs (“VA”) construction project located in Philadelphia. Nason was the general contractor, Zurich was Nason’s surety, and Marenalley was Nason’s subcontractor. Marenalley’s subcontract required it to pursue any claim related to the project through the administrative disputes resolution process provided by Nason’s prime contract with the VA before bringing suit against the project’s bond.  The prime contract’s administrative dispute resolution process clause incorporated the terms of the Contract Disputes Act (the “CDA”).