SAK & Assocs. v. Ferguson Constr., Inc., 189 Wn. App. 405 (Wash. Ct. App. 2015)

Ferguson Construction, Inc. (“General Contractor”) entered into a fixed sum contract (the “Subcontract”) with SAK & Associates (“Subcontractor”) to provide concrete materials and paving services (the “Work”).  The Subcontract included a termination for convenience clause providing that General Contractor could terminate Subcontractor for convenience upon written notice.  After Subcontractor completed 24 percent of the Work, General Contractor terminated Subcontractor.  General Contractor paid Subcontractor 24 percent of the fixed contract price for the work Subcontractor actually completed.

King County v. Vinci Construction Grands Projects/Parsons RCI/Frontier-Kemper, JV, 2015 Wash. App. LEXIS 2735 (Nov. 9, 2015)

The Court of Appeals of Washington recently decided King County v. Vinci Construction Grands Projects/Parsons RCI/Frontier-Kemper, JV, a dispute between a joint venture contractor (the Contractor) and King County, Washington (the County). The dispute stemmed from problems that arose and significant delays that occurred during a major expansion of the County’s wastewater treatment system, known as the Brightwater project. The case illustrates the potential pitfalls of a contractor’s claim of differing site conditions.

Oakdale Equip. Corp. v. Meadows Landing Assocs., LP, 2015 Pa. Super. Unpub. LEXIS 2067 (Pa. Super. Ct. July 8, 2015)

Meadows Landing Associates, LP (“MLA”) contracted with Richard Lawson Excavating, Inc. (“Lawson”) for work on MLA’s 200-acre subdivision, including earthwork, grading, excavating and pond construction.  Lawson then contracted with Oakdale Equipment Corporation (“Oakdale”) to rent heavy equipment for the work.  More than one year later, MLA terminated Lawson for failure to achieve substantial completion on time.  Oakdale and Lawson both filed mechanics’ lien claims against MLA.

Elliot-Lewis Corp. v. Skanska USA Building, Inc., 2015 U.S. Dist. LEXIS 98405 (E.D. Pa. July 27, 2015)

This dispute arises out of a major renovation and expansion of the Franklin Institute in Philadelphia (the “Project”).  Plaintiff Elliot-Lewis Corporation (“ELCo”) was a subcontractor hired to install the piping and controls for the Project’s heating, ventilation and air conditioning (“HVAC”) system.  The Project’s schedule required that start up and testing of the HVAC system begin by February 23, 2013 and that the system be operational by April 1, 2013.  But, when the HVAC was started for testing, flooding issues arose due to problems with the condenser pumps specified in the HVAC system’s specifications.  Ultimately, the HVAC system was not operational by April 1 and ELCo was required to perform additional work and install temporary cooling equipment so that the Franklin Institute could open during the summer.  ELCo was never paid by the prime contractor for this additional work.

On August 31, 2015, highway contractors Trinity Industries, Inc. and Trinity Highway Products, LLC (collectively, Trinity) appealed to the U.S. Court of Appeals for the Fifth Circuit a $663,360,750 final judgment entered against them under the federal False Claims Act (FCA). At the conclusion of a six-day trial that commenced on October 13, 2014, the jury rendered a unanimous verdict, finding Trinity “knowingly made, used, or caused to be made or used, a false record of statement material to a false or fraudulent claim” in violation of the FCA. The jury unanimously found that the U.S. government suffered damages in the amount of $175,000,000 as the result of Trinity’s FCA violations.

DVBE Trucking and Construction Co., Inc. v. McCarthy Building Companies, Inc., 2015 U.S. Dist. LEXIS 90052 (N.D. Cal. July 10, 2015)

This payment dispute case arises out of a Veterans Affairs (“VA”) construction project located in Palo Alto, California.  McCarthy Building Companies, Inc. (“McCarthy”) was the prime contractor, Federal Insurance Company and Travelers Casualty and Surety provided the performance and payment bonds on behalf of McCarthy mandated by the Miller Act, and DVBE Trucking and Construction Company, Inc. (“DVBE”) was McCarthy’s subcontractor.  Section 11.1 of DVBE’s subcontract required that, for any dispute involving the VA, it would follow the dispute resolution procedures agreed to by McCarthy in its contract with the VA, and agreed to be bound by the result of any such dispute resolution procedures to the same degree as McCarthy.

Davis Group, Inc. v. Ace Electric, Inc., 2015 U.S. Dist. LEXIS 83368 (M.D. Fla. June 26, 2015)

This action arose out of a construction project to build a new Radar Approach Control Facility at Seymour Johnson Air Force Base in Goldsboro, North Carolina (“Project”). The United States Army Corps of Engineers (“COE”) contracted with general contractor Davis Group, Inc. (“TDG”) to construct the Project. TDG entered into a subcontract with Ace Electric, Inc. (“Ace”) to perform the electrical work on the Project (the “Subcontract”).

The Subcontract included various provisions addressing delays in completion of the work. In particular, the parties agreed that Ace was entitled to a reasonable extension of time and/or additional compensation if its work was delayed, through no fault of Ace, by the COE, TDG or other subcontractors. If on the other hand, Ace was responsible for a delay in completion of the work, then the parties agreed that Ace would “reimburse [TDG] for the entire cost and expense suffered or incurred as a result of” the delay, including any liquidated or other damages the COE might assess against TDG for delays to the Project as a whole. The Subcontract further provided that, if “such damages are caused by [Ace] and another person or entity,” TDG could “reasonably apportion such damages between the parties, and any such apportionment shall be final and binding upon [Ace].”

Wax NJ-2, LLC v. JFB Constr. & Dev., 13-cv-4537, 2015 U.S. Dist. LEXIS 74508 (S.D.N.Y. June 9, 2015)

Wax NJ-2, LLC (“Wax”) hired the architectural firm GF55 Partners (“GF55”) to design and then inspect construction of a store that Wax planned to open in New York City.  The building which Wax was preparing to lease for the store had been leased as two separate commercial spaces.  Wax had the option of moving a partition wall between the two spaces and thus increasing or decreasing the amount of square footage leased for its store.  In designing the layout of Wax’s store, GF55 reported to Wax that the footprint called for 1235 square feet.  Wax then entered into a lease agreement with the owner for 1235 square feet of the building at $125 per square foot.  Construction commenced, and GF55’s remaining obligations under its contract with Wax included inspection of the contractor’s work to ensure compliance with the building code.

Vanguard Constr., Inc. v. United States, 2015 U.S. Claims LEXIS 1158 (Fed. Cl. Sep. 8, 2015)

The United States Air Force (the “Government”) entered into a contract with Vanguard Construction, Inc. (“Contractor”) to replace a roof (the “Contract”).  The Contract incorporated by reference portions of the Federal Acquisition Regulation (FAR).

Contractor’s demolition of the existing roof revealed that a significant section of the roof stem wall was missing.  The Contract did not address the contingency of a missing stem wall.  Contractor sent the Government several letters asking for guidance on how to proceed, including a request for information on structural requirements for building a stem wall.  The Government refused to provide the requested information, asserting that the terms of the contract allocated to the Contractor the risk of dealing with latent or unanticipated site conditions and the burden of devising a solution to the problem.

John Spearly Constr., Inc. v. Penns Valley Area Sch. Dist., 2015 Pa. Commw. LEXIS 337 (Pa. Commw. Ct. July 24, 2015)

This action arose out of the construction of a biomass boiler system for the Penns Valley Area School Districts (“District”) to house the District’s boiler plant  (“Project”).  The District contracted with general contractor John Spearly Construction, Inc. (“Contractor”) to construct the Project. The District entered into direct contracts with the Project Architect and other contractors responsible for other components of the work.

Construction began in July 2010 and was to be substantially completed no later than October 18, 2010.  From its inception, however, the Project was plagued with delays.  Project delays were caused by, among other things, delays by the District’s Architect in deciding on and responding to submittals relating to changes, disputes between the District and its HVAC contractor responsible for delivering the boiler, and work performed by a sewer contractor the District brought in toward the end of the Project to repair and replace storm water and sewer pipes. Ultimately, the Project was not substantially completed until August 11, 2011.