Aquatic Renovations Sys. v. Vill. of Walbridge, 2018 Ohio App. Lexis 1581 (April 13, 2018)

This post was published on July 7, 2018 in The Pennsylvania Record.

On May 2, 2012, Aquatic Renovations Systems, Inc. (“Aquatic”) entered into a contract with the Village of Walbridge (“the Village”) for the installation of a new pool liner (“Contract 1”).  Prior thereto, the Village council adopted an ordinance which authorized the mayor to enter into Contract 1 (“Ordinance”).  On April 12, 2013, the mayor signed a new contract for the balance of the work (“Contract 2”).  A few days after Aquatic completed its work, the pool liner began to lift.  The Village then refused to pay Aquatic for the completed and approved work.

Aquatic sued the Village for non-payment, alleging the Village breached Contract 2.  Aquatic also alleged that the Village was liable under a theory of quantum meruit and unjust enrichment.  The trial court granted the Village’s motion for summary judgment, holding that Contract 2 was not valid because it did not comply with the Ohio Revised Statute which required the mayor, the clerk, and the Village administrator to authorize all Village Contracts.  Thus, because Contract 2 was unenforceable, Aquatic could not recover under a breach of contract, quantum meruit or unjust enrichment theory.

United States Home Corp. v. Ballesteros Trust, 2018 Nev. LEXIS 28 (Nev. Apr. 12, 2018)

United States Home Corporation (“U.S.H.”) built homes in a Nevada common-interest community, subject to a Covenant, Conditions, and Restrictions agreement (“CC&R”), which provided that any dispute would be resolved by arbitration.

Between August 2013 and February 2015, twelve home purchasers filed pre-litigation notices against U.S.H. for alleged construction defects.  Three of the purchasers had direct purchase and sales agreements with U.S.H. that contained arbitration clauses; the remaining homeowners did not sign such agreements, but took title subject to the CC&R.  U.S.H. demanded arbitration, but the homeowners brought claims in a Nevada district court seeking damages for breach of contract and other claims.  U.S.H. moved to compel arbitration.  The court held that the transaction did not involve interstate commerce, so the Federal Arbitration Act (“FAA”) did not apply, and invalidated the arbitration agreements as unconscionable.

Fraser Eng’g Co. v. IPS-Integrated Project Servs., LLC, 2018 US Dist. LEXIS 51392 (D.N.H. March 27, 2018)

IPS-Integrated Project Services, LLC (“IPS”) was the general contractor on a project to design and construct a manufacturing facility in Portsmouth, New Hampshire. IPS subcontracted with Fraser Engineering Company (“Fraser”) for the project’s mechanical and plumbing scope of work. Shortly after award, IPS notified Fraser that it may be directed to accelerate its work. In response, Fraser put IPS on notice that acceleration would result in labor inefficiencies for which it expected to be reimbursed.  Thereafter, IPS directed Fraser to accelerate and Fraser complied by using extra overtime over the next several months. During that time, the parties communicated numerous times about Fraser’s claim for labor inefficiencies.

Under its subcontract with IPS, Fraser was required to submit lien waivers with each of its payment applications. According to the court, the waivers at issue “do not merely release lien rights, but also ‘all claims, demands, or causes of action . . . which [Fraser] has, or might under any present or future law, assert against [IPS] or [the owner] relating to the Partial Payment and/or the labor services, materials or equipment for which the partial payment has been made.’” During its work, Fraser submitted eight such waivers.

Pavik v. George & Lynch, Inc., No. 160, 2017, 2018 Del. LEXIS 133 (Mar. 23, 2018)

This case arises out of a highway reconstruction project and a car accident which occurred on the highway during non-working hours.  The Delaware Department of Transportation (“DelDOT”) hired George & Lynch, Inc. (“G&L”) to repave Omar Road.  The contract obligated G&L to perform its work in a manner that would provide reasonably safe passage to the traveling public and to provide for the protection and safety of the general public.  DelDOT approved G&L’s traffic control plan, which provided for placement of temporary warning signs during working hours and permanent warning signs advising travelers of road work ahead.  As part of its work, G&L performed cold in-place recycling, a process by which asphalt is removed, recycled, and reapplied as a base layer.  As the recycled asphalt cures, the road surface can support traffic, but there is a risk that raveling—a condition in which the base layer breaks apart—can occur.

It was during a curing period that the accident occurred.  On Friday, after asphalt had been installed and began to cure, the road was reopened.  On Saturday, after a thunderstorm, DelDOT received complaints of potholes on the road.  On Sunday, DelDOT patched the potholes and later that night, the driver lost control of her car and ran off the road.  Plaintiffs claimed the accident was caused by raveling and that G&L was negligent because it failed to provide warning signs about the road’s condition during the non-working hours.  G&L argued that it had no duty to erect additional signs and that DelDOT’s repairs broke the chain of causation.

City of Whiting v. Whitney, Bailey, Cox & Magnani, LLC, 2018 U.S. Dist. LEXIS 44943 (N.D. Ind. Mar. 20, 2018)

The City of Whiting, Indiana (the “City”) undertook a 26-acre lakefront development project.  It hired an engineering firm to serve as the consultant for the project.  The consultant subcontracted with a subconsultant for marine engineering services, including design of a rock revetment on the lakefront for shoreline protection.  According to the City, the revetment failed on three occasions, resulting in damage to the City’s property at the project site, including a walking path, landscaping and existing trees, a gazebo, and an existing Gun Club structure, which the City had planned to convert to a restaurant.

After accepting assignment of the consultant’s contract with the subconsultant, the City filed a six-count complaint and alleged that the subconsultant’s negligent revetment design caused damage to the City’s property.  The subconsultant moved for summary judgment on the City’s negligence claim, arguing that the economic loss rule precluded liability against it in tort.  The court noted that Indiana’s economic loss rule bars tort liability when there is damage only to the product contracted for itself, but that the rule does not preclude tort liability if there is personal injury or damage to “other property.”

G&G Mech. Constructors, Inc. v. Jeff City Indus., Inc., No. WD80840, 2018 Mo. App. LEXIS 271 (Mar. 20, 2018)

This case arose out of a project in Columbia, Missouri on which Jeff City Industry, Inc. (“JCI”) was the general contractor and G&G Mechanical Constructors, Inc. (“G&G”) was a subcontractor.

The draft subcontract contained an interest provision which provided that overdue payments “shall bear interest at the annual rate of 18% or the highest rate allowed by law, if lower. Retainage shall not be held out of payment.”  JCI struck through this provision, wrote “5% Retiange [sic]” in the margin, initialed it, and sent it to G&G.  G&G also initialed the revision.

When JCI failed to pay G&G for its work, G&G sued JCI for breach of contract, unjust enrichment, and violation of Missouri’s Prompt Pay Act.  A jury returned a verdict against JCI, and the trial court entered a judgment against it which included prejudgment interest at the rate of 9% pursuant to Missouri Revised Statute § 408.020.

Meridian Eng’g Co. v. United States, 2018 U.S. App. LEXIS 7024 (Fed. Cir., Mar. 20, 2018)

Meridian Engineering Company (“Meridian”) was hired by the United States (“Government”) to construct flood control structures on the Chula Vista Project.  Meridian encountered what it considered to be differing site conditions on the project.  The Government issued two contract modifications in response to Meridian’s claims.  Later, structural failures occurred and the Government ultimately terminated Meridian.  Meridian filed suit in the Court of Federal Claims.

The court held that Meridian failed to establish a compensable differing site condition because the bid documents sufficiently notified contractors of potential water conditions at the site that could result in the conditions claimed.  Also, the court held that Meridian was charged with knowledge of the conditions that a pre-bid site visit would have revealed, which included the conditions in question.  The Court of Appeals affirmed the trial court on that issue.

Suffolk Constr. Co. v. Rodriguez & Quiroga Architects Chtd., 2018 U.S. Dist. LEXIS 42652 (S.D. Fla. Mar. 15, 2018)

This case arises out of the design and construction of a science museum in Miami, Florida (the “Project”).  Museum of Science, Inc. (“MSI”), the Project owner, executed several agreements relating to the Project, including: (i) an agreement with Defendant Rodriguez and Quiroga Architects Chartered (“R&Q”) to serve as executive architect; (ii) an agreement with Defendant Grimshaw Architects P.C. (“Grimshaw”) to serve as the design architect; (iii) a construction services contract with Plaintiff Suffolk Construction Co. (“Suffolk”); and (iv) a direct contract with Suffolk’s subcontractor, Plaintiff Baker Concrete Construction, Inc. (“Baker”) for construction services after MSI terminated Suffolk for convenience.  After execution of these agreements, R&Q executed contracts with Defendant Fraga Engineers, LLC (“Fraga”) for mechanical, electrical, and plumbing design services, and with Defendant DDA Engineers, P.A. (“DDA”) for structural design and engineering services.

Suffolk and Baker (collectively, “Plaintiffs”) filed suit for negligence against R&Q, Grimshaw, Fraga, and DDA (collectively, “Defendants”), claiming that by issuing deficient design documents, Defendants breached their duties owed to Plaintiffs causing Plaintiffs to incur economic losses.  All Defendants but R&Q moved to dismiss the claims, arguing that they had no supervisory role or control over Plaintiffs, as demonstrated by the fact that their contracts with MSI did not designate them as “supervisory architects,” and thus, owed no duty to Plaintiffs.

Transocean Offshore Gulf of Guinea VII Ltd. v. Erin Energy Corp., 2018 U.S. Dist. LEXIS 39494 (S.D. Tex. Mar. 12, 2018)

On March 12, 2018, in Transocean Offshore Gulf of Guinea VII Ltd. v. Erin Energy Corp., the U.S. District Court for the Southern District of Texas became the second U.S. court to recently determine that the 1958 New York Convention on the Recognition and Enforcement of Foreign Arbitral Awards (the “New York Convention”), as codified in the Federal Arbitration Act (“FAA”), applies to consent awards.  Although seemingly inconsequential at first glance, the question of whether consent awards—i.e., settlement agreements recorded by arbitral tribunals as awards—are subject to the New York Convention, has remained the subject of much debate within the field of international arbitration for many years.

In Transocean, the petitioners, Transocean Offshore Gulf of Guinea VII Limited and Indigo Drilling Limited, entered into an agreement to provide drilling equipment, personnel, and services in the waters off the coast of Nigeria to the respondent, Erin Energy Corporation.  Prior to the completion of the contract, a dispute arose and, pursuant to an arbitration clause, the petitioners initiated an arbitration under the rules of the London Court of International Arbitration (“LCIA”).  Before the tribunal made a decision on the merits, the parties reached a settlement and, at the parties’ request, the tribunal issued a consent award setting forth the terms of the parties’ settlement.

Hope v. Dep’t of Veterans Affairs, 2018 U.S. Dist. LEXIS 28479 (E.D. Ark. Feb. 22, 2018)

This matter involved a motion for temporary restraining order and preliminary injunction (the “Motion”) filed by Richard Alan Hope (“Hope”) and his HVAC company, Powers of Arkansas (“Powers”), asking the District Court to prohibit the Department of Veterans Affairs (“VA”) from continuing debarment proceedings against them.  In 2012, Federal agents began investigating Hope for fraudulently presenting DAV Construction Company, Inc. as a legitimate service-disabled, veteran-owned small business in order to obtain government construction contracts.  Hope was indicted in 2016 for conspiracy to defraud, among other things.  The VA thereafter suspended Hope and Powers from government contracting based on the indictment.  The indictment was ultimately dismissed after the Court declared a mistrial.  In January of 2018, the VA lifted the suspensions, but issued notices of proposed debarment to Hope and Powers.  While debarment proceedings are pending, a contractor may not be awarded government contracts.
The Court first analyzed jurisdiction.  Absent waiver, sovereign immunity shields the VA from suit.

However, the Administrative Procedure Act (“APA”) waives sovereign immunity to allow judicial review of final agency actions.  The Court held that it lacked jurisdiction here because there was no final agency decision as to the proposed debarment.  Indeed, the VA has established procedures for debarment decisions and the proposal for debarment is only the first step.  The Court found that because the VA’s decision-making process had only just begun, and there had been no final agency action, the APA did not authorize the Court to review the merits of the proposed debarment at this time.