Philadelphia Auth. for Indus. Dev. v. United States, 114 Fed. Cl. 519 (2014)

In this action, the United States Court of Federal Claims denied the Government’s motions to dismiss and for summary judgment, holding that plaintiff had sufficiently pled and supported claims against the Government based upon misrepresentations and omissions in data supplied by the Government in a negotiated procurement.  The Court held that negligent estimate, superior knowledge, misrepresentation and mutual mistake were viable theories upon which to pursue such a claim.  It rejected the Government’s position that a claim for negligent estimate could not be maintained in the context of a negotiated procurement, and also held that the plaintiff’s expectation of a limited loss did not negate the element of reliance with respect to much larger losses attributable to undisclosed or misrepresented information.

Frontier Contr. Inc. v. Allen Eng’g Contr., Inc., 2014 U.S. Dist. LEXIS 136474 (E.D. Cal. Sept. 2014)

Frontier Contracting Inc. (Frontier) entered into a teaming agreement with Allen Engineering Contractor, Inc. (Allen) to complete two U.S. Federal Highway projects in Sequoia and Kings Canyon National Parks.  During the course of the projects, disputes arose and Allen refused to issue full payments to Frontier.  Frontier then filed a complaint against Allen alleging, in part, a Miller Act claim.

Wyman v. Ayer Properties, LLC, 469 Mass. 64,  2014 Mass. LEXIS 524 (July 10, 2014)

The Massachusetts Supreme Court ruled that the economic loss rule, which bars recovery of tort damages from the negligent supplier of a defective product when there is no claim of personal injury or damage to other property, does not apply to claims asserted by a condominium association or similar condominium organization seeking compensation for damage to common areas of a condominium building caused by defective construction.

This case arises out of a dispute between the Market Gallery Condominium Trust, the trustees responsible for management of a condo building, and Ayer Properties, the developer and builder of the condo building, after the trustees observed that Ayer had negligently constructed the window frames, the exterior brick masonry, and the roof of the building. The trustees commenced an action alleging that the negligent construction caused damage to both the common areas and the residential units in the building.

Bedwell Co. v. Camden County Improvement Auth., 2014 U.S. Dist. LEXIS 95510 (D.N.J. July 14, 2014)

The University of Medicine and Dentistry of New Jersey contracted HDR Architects and Engineers, P.C. (“HDR”) to design a medical school building. After the project went to bid, the Bedwell Company (“Bedwell”) contracted with the owner’s development and contracting agent for the performance of foundation, structural steel, and other construction work.

Bedwell and HDR did not have a contract with each other. According to the allegations in Bedwell’s complaint, however, HDR was aware that the design documents that it prepared under its contract with the owner would be used by contractors like Bedwell in their estimation of costs and time for completion of the work. In its complaint, Bedwell alleged that defects in HDR’s design documents—which led to 212 Requests for Information and 469 Change Order Requests—caused unexpected costs and numerous delays.

United States ex rel. Heggem-Lundquist Paint Co. v. Centerre Gov’t Contracting Grp., LLC, 2014 U.S. Dist. LEXIS 66161 (D. Colo. Apr. 23, 2014) 
 Am. Constr. & Envtl. Servs. v. Total Team Constr. Servs., Inc., 2014 U.S. Dist. LEXIS 57467 (E.D. Cal. Apr. 23, 2014)

Federal district courts for the District of Colorado and the Eastern District of California have ruled  subcontract provisions that disputes will be resolved in accordance with the dispute resolution provisions in a prime contract are insufficient to waive or postpone a subcontractor’s Miller Act rights.

These cases involved claims asserted by subcontractors (collectively “Plaintiffs”) against the upstream contractors and their sureties (collectively “Defendants”) for work performed on federal government projects.  The plaintiff in Haggem-Lundquist performed as a sub-subcontractor on a Department of Veterans Affairs renovation project at a medical center in Denver, Colorado.  The plaintiff in Am. Constr. & Envtl. Servs. performed as a subcontractor in support of a contract with the Army Corps of Engineers to replace emergency generators at a Veterans Administration Care Facility in Fresno, California.  In both actions, Plaintiffs filed claims against the bonds issued for the projects pursuant to the Miller Act to recover money allegedly owed for changed and additional work performed.

Technica LLC v. Carolina Casualty Ins. Co., 749 F.3d 1149,2014 U.S. App. LEXIS 8023 (9th Cir., April, 29, 2014)

This payment dispute arose out of the ICE El Centro SPC – Perimeter Fence Replacement/Internal Devising Fence Replacement federal project in California.  Candelaria was the prime contractor.  Candelaria entered into subcontract with Otay, who contracted with Technica to act as a sub-subcontractor.  After submitting invoices for labor, material and services, Technica received only partial payment for its work.

Technica filed a Miller Act claim authorized by federal statute  to recover the outstanding amount owed on its sub-subcontract against Candelaria’s payment bond.  Candelaria and its surety filed a motion for summary judgment, arguing that the California Business and Professions Code precludes any contractor from maintaining a collection action, unless the contractor was licensed during the performance of the contract.  Since Technica lacked a California contactor license, the district court held that Technica could not pursue a Miller Act claim.

In re Kellogg Brown & Root, Inc., 2014 U.S. App. LEXIS 12115 (D.C. Cir. June 27, 2014)

The United States Court of Appeals for the District of Columbia Circuit held that the attorney-client privilege applies to internal investigations performed at the direction of in-house counsel if “one of the significant purposes” of the investigation was to obtain or provide legal advice.

Kellogg Brown & Root, Inc. (“KBR”) was a defense contractor for the United States government. Harry Barko, a former employee of KBR, filed a False Claims Act complaint against KBR, alleging fraud against the government. During the ensuing litigation, Barko requested documents related to KBR’s prior internal investigation into the alleged fraud. The investigation had been conducted by KBR pursuant to Department of Defense regulations that require defense contractors to maintain compliance programs and conduct internal investigations, and was overseen by the company’s in-house legal department. KBR objected to the document request, arguing that the investigation was protected by the attorney-client privilege. In turn, Barko argued that the documents were discoverable business records not covered by the privilege.

Metcalf Constr. Co. v. United States
742 F.3d 984 (Fed. Cir. 2014)

This action arose out of the design and construction of military housing units at a U.S. Navy facility in Hawaii.  Pre-bid documents for the project supplied by the government provided test information regarding soil conditions on the site.  The government also included a disclaimer that this information was “for preliminary information only” and the resulting contract required that the contractor conduct its own independent soil investigation.

Metcalf Construction Company (the “Contractor”) was awarded the contract.  When the Contractor conducted its independent soil investigation it discovered that the soil was not as represented.  The Contractor notified the government and discussions ensued.  In those discussions, the Contractor recommended a different design and construction approach to account for the newly uncovered conditions, while the government generally insisted on following construction requirements set out in the original contract.  After a year’s delay, the Contractor decided that the cost of waiting for the government to approve the design changes had become too high, and it began to implement those changes without a contract modification.  As a result, the Contractor spent approximately $26 million over the original contract amount to remedy the soil conditions and finish the project.

United States ex rel. Tymatt Indus. v. Allen & Shariff Constr. Servs.
2013 U.S. Dist. LEXIS 114015 (D. Md. Aug. 13, 2013)

This action arose out of a subcontractor’s Miller Act claim for unpaid contract balances on a federal construction project. Allen & Shariff Construction Services, LLC (“Allen & Shariff”) was the prime contractor on a federal contract for the construction of a dam in Bethesda, Maryland, and related remediation (the “Project”). United States Security Company (“USSC”) was the surety on the Miller Act payment bond for the Project. Allen & Shariff subcontracted with Tymatt Industries, Inc. (“Tymatt”) to perform work on the Project (the “Subcontract”). The Subcontract contained a default provision stating that “should Tymatt fail to perform, after giving three days written notice Allen & Shariff had the option to terminate the [S]ubcontract for default if the defective performance was not cured.” Allen & Shariff issued three such notices to Tymatt, the last of which was issued on November 11, 2011. When Tymatt failed to cure, USSC sent Tymatt a termination notice on November 18, 2011 stating that the “[S]ubcontract…has been terminated due to lack of performance effective immediately.” Additionally, Allen & Shariff notified Tymatt that its “base access privilege [would] be terminated on November 23, 2011,” and requested that its equipment be removed prior to that date. Tymatt subsequently alleged that Allen & Shariff failed to pay $107,665.26 in amounts owed for work performed under the Subcontract. On Monday, November 26, 2012, Tymatt filed a Miller Act claim against USSC, as surety, to recover the monies allegedly due and owing.

United States of America ex rel D&M General Contracting, Inc v. Arch Ins. Co.
2013 U.S. Dist. LEXIS 111260 (D. Md. Aug. 5, 2013)

This action arose out of subcontractor’s claim for increased costs allegedly incurred as a result of delays on a federal government project. NTVI Enterprises, LLC (“NTVI”), as general contractor, entered into an agreement with the government to upgrade the chiller plant for a National Security Agency facility (the “Project”). NTVI posted a labor and material payment bond for the Project (the “Bond”) issued by Arch Insurance Company (“Arch”). NTVI then subcontracted with D&M General Contracting, Inc. (“D&M”) to perform electrical work on the Project. Midway through the Project, D&M alleged that the sequence of its work was altered by the government resulting in an additional $206,674.07 in costs to D&M. Pursuant to the Miller Act, D&M filed suit against Arch, as surety, to recover under the Bond its increased costs allegedly incurred.