Time is money in construction, and project delays can cause contractors to incur substantial additional costs. To avoid responsibility for paying these costs, project owners often include a no-damage-for-delay (NDFD) clause in the contract, where legally permitted.[1] An example of a typical NDFD clause reads as follows:

The Contractor agrees to make no claim for damages for delay in the performance of this contract occasioned by any act or omission to act of the [Owner] or any of its representatives, and agrees that any such claim shall be fully compensated for by an extension of time to complete performance of the work as provided herein.[2]

An NDFD clause may bar a contractor from recovering delay damages. But, in most states, the enforceability of NDFD clauses is also subject to exceptions.[3] As shown in the clause quoted above, NDFD clauses often provide that the exclusive remedy for delay is an extension of time. The issue is whether an NDFD clause, which provides a time extension as an exclusive remedy, also bars claims for acceleration. As explained below, there are several approaches to this issue.

Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP, 226 Md. App. 420, 130 A.3d 1024, 2016 Md. App. LEXIS 3 ( Md. Ct. Spec. App. Jan. 28, 2016)

The City of Baltimore retained a design professional, Rummel Klepper & Kahl (“RK&K”), to produce a design for construction of a wastewater treatment plant.  The City then invited bids for construction of the plant, and contractor Balfour Beatty Infrastructure (“Balfour Beatty”) was the successful bidder.  RK&K and Balfour Beatty each had a separate contract with the City, but did not have a contract with one another.  After alleged defects in RK&K’s design caused Balfour Beatty to incur delays and increases to the cost of its work, it sued RK&K, but not the City.

Pavarini Construction Co. v. Ace American Insurance Co., 2015 U.S. Dist. LEXIS 151247 (S.D. Fla. Oct. 29, 2015)

This action arose out of a construction project to build a 63-story luxury condominium tower located in Miami, Florida (“Project”).  Pavarini Construction Co. (“Pavarini”) was the general contractor for the construction of the Project.   Pavarini hired a subcontractor for the installation of the concrete masonry unit walls and certain reinforcing steel, and a second subcontractor for the supply and installation of reinforcing steel within the cast-in-place concrete columns, beams, and sheer walls. The work performed by both of these subcontractors was deficient.  A significant amount of reinforcing steel was either omitted entirely or improperly installed, including within important concrete structural elements, resulting in destabilization throughout the building.  This, in turn, caused stucco debonding and cracking on the walls of the building, worsening cracking of cast-in-place concrete elements, and cracking in the mechanical penthouse enclosure on the roof, which led to water infiltration.

City of Whiting, Indiana v. Whitney, Bailey, Cox, & Magnani, LLC, 2015 U.S. Dist. LEXIS 150229 (N.D. Ind. Nov. 5, 2015)

The City of Whiting, Indiana (the “City”) contracted with American Structurepoint, Inc. (“Engineer”) to design a lakefront park that would protect its shoreline from erosion (the “Project”).  Engineer subcontracted with Whitney, Bailey, Cox, & Magnani, LLC (“Subconsultant”) to serve as the marine engineer for the Project (the “Subcontract”).  Pursuant to the Subcontract, Subconsultant designed a revetment to protect the Project shoreline.  The revetment failed, damaging the City’s property and necessitating remediation.

Apex Directional Drilling, LLC v. SHN Consulting Eng’rs & Geologists, Inc., 2015 U.S. Dist. LEXIS 105537 (N.D. Cal. Aug. 11, 2015)

The United States District Court for the Northern District of California held that an engineer that prepares plans and specifications to be relied upon by contractors in preparing their bids for a construction project owes a duty of care to those contractors, and therefore can be held liable to the contractors for breach of professional duty and/or negligent misrepresentation.

King County v. Vinci Construction Grands Projects/Parsons RCI/Frontier-Kemper, JV, 2015 Wash. App. LEXIS 2735 (Nov. 9, 2015)

The Court of Appeals of Washington recently decided King County v. Vinci Construction Grands Projects/Parsons RCI/Frontier-Kemper, JV, a dispute between a joint venture contractor (the Contractor) and King County, Washington (the County). The dispute stemmed from problems that arose and significant delays that occurred during a major expansion of the County’s wastewater treatment system, known as the Brightwater project. The case illustrates the potential pitfalls of a contractor’s claim of differing site conditions.

Wax NJ-2, LLC v. JFB Constr. & Dev., 13-cv-4537, 2015 U.S. Dist. LEXIS 74508 (S.D.N.Y. June 9, 2015)

Wax NJ-2, LLC (“Wax”) hired the architectural firm GF55 Partners (“GF55”) to design and then inspect construction of a store that Wax planned to open in New York City.  The building which Wax was preparing to lease for the store had been leased as two separate commercial spaces.  Wax had the option of moving a partition wall between the two spaces and thus increasing or decreasing the amount of square footage leased for its store.  In designing the layout of Wax’s store, GF55 reported to Wax that the footprint called for 1235 square feet.  Wax then entered into a lease agreement with the owner for 1235 square feet of the building at $125 per square foot.  Construction commenced, and GF55’s remaining obligations under its contract with Wax included inspection of the contractor’s work to ensure compliance with the building code.

Gongloff Contracting, L.L.C. v. L. Robert Kimball & Assocs., Architects and Eng’rs, Inc., 2015 Pa. Super 149 (Pa. Super. Ct. July 8, 2015)

Pennsylvania law generally bars negligence claims when the injured party has suffered only economic losses.  This principle is commonly referred to as the economic loss doctrine.  An exception to this doctrine is found in Section 552(1) of the Restatement (Second) of Torts, which provides that, “one who, in the course of his business, profession or employment … supplies false information for the guidance of others in their business transactions, is subject to liability for pecuniary loss caused to them by their justifiable reliance upon the information, if he fails to exercise reasonable care or competence in obtaining or communicating the information.” In Bilt-Rite Contractors, Inc. v. Architectural Studio, 581 Pa. 545 (2005), the Pennsylvania Supreme Court adopted this exception and found it to be applicable in cases where information is negligently supplied by an architect or design professional under circumstances where it is foreseeable that others will rely upon that information.  In Gongloff, the Superior Court of Pennsylvania, interpreting Bilt-Rite, held that the Bilt-Rite exception can be triggered when an architect or design professional negligently includes faulty information in its design documents.  The Gongloff court rejected the argument that, under Bilt-Rite, an injured party is required to identify an “express” misrepresentation in a particular communication or document in order to support a claim of negligent misrepresentation.

USA Walnut Creek, DST v. Terracon Consultants, Inc. f/k/a HBC Engineering, Inc., 2015 Tex. App. LEXIS 1806 (Tex. App. 2015)

This cases arises out of the construction of a twelve building apartment complex in Austin Texas.  The builders, Creekstone Walnut, LP and Creekstone Builders, Inc., contracted with defendant Terracon for geotechnical engineering and inspection services.  As part of the services, Terracon performed test borings and provided the geotechnical recommendations for, among other things, the foundation design.  Terracon’s inspection services included providing testing and inspection of the construction materials, including compaction testing on the earthwork.

East Coast Paving & Sealcoating, Inc. v. N. Allegheny Sch. Dist., 111 A.3d 220 (Pa. Commw. Mar. 6, 2015).

North Allegheny School District (“Owner”) hired East Coast Paving & Sealcoating, Inc. (“Contractor”) to pave several large areas.  Shortly after Contractor began its paving work, Owner’s architect found “soft spots” in the areas to be paved.  Contractor’s scope of work under the contract did not include soft spot repair work, in which soft ground is replaced with compacted stone before paving, but Contractor and Owner’s Director of Facilities, who had the authority to authorize additional work, agreed that Contractor would do the repair work.  Owner’s architect’s finding of soft spots and Owner’s Director of Facilities’ agreement with Contractor were documented in a report to Owner.  A second report to Owner documented Contractor’s commencement of the repair work.