Great N. Ins. Co. v. Honeywell Int’l, Inc., No. A16-0997, 2018 Minn. LEXIS 236 (May 9, 2018)

This case arises out of a residential construction project and the installation of ventilators into a home’s HVAC system.  Sixteen years after completion of the work, a fire occurred in one of the ventilators, causing property damage.  After paying the homeowners’ insurance claim, Great Northern Insurance (“Great Northern”), as subrogee, filed suit against McMillan Electric Company (“McMillan”), the manufacturer of the motors in the ventilators, asserting claims for product liability, breach of warranty, and negligence, including a claim for breach of a post-sale duty to warn consumers of the risk of fires in ventilator motors.

The trial court granted McMillan summary judgment concluding that Minnesota’s 10-year statute of repose barred all of Great Northern’s claims except for the post-sale duty to warn claim, which also failed because McMillan owed no such duty. The Court of Appeals reversed both holdings.  On appeal, the Supreme Court affirmed the Court of Appeals’ decision that McMillan’s motor was “machinery,” to which the statute of repose does not apply.

Woodrow Wilson Constr. LLC v. Orleans Par. Sch. Bd.,  2018 La. App. LEXIS 762 (April 18, 2018)

The Orleans Parish School Board (“OPSB”) awarded a prime contract to Woodrow Wilson Construction (“WWC”) for the construction of a new elementary school (the “Project”).  On May 23, 2016, WWC submitted its request for payment of final retainage to OPSB.  OPSB withheld payment from WWC, claiming that WWC owed liquidated damages for the delays in completion of the Project, which allegedly exceeded the amount due to WWC.  WWC filed a petition for writ of mandamus pursuant to La. R.S. 38:2191(D) (the “Act”), which provides that “[a]ny public entity failing to make any … any final payment when due as provided in this Section, shall be subject to mandamus to compel the payment of the sums due under the contract …”  The trial court denied the petition and WWC appealed.  The question on appeal was whether OPSB may withhold final payment due under the Act because of alleged delays in the Project, despite the fact that liability for the delays had not yet been adjudicated.

Section A of the Act provides that “[a]ll public entities shall promptly pay all obligations arising under public contracts when the obligations become due and payable under the contract.  All … final payments shall be paid when they respectively become due and payable under the contract.”  Under the prime contract, retainage was due upon the occurrence of six enumerated requirements.  The Court determined that these requirements were all satisfied as of May 23, 2016 and therefore final retainage was due to WWC as of that date.  The Court further found that upon satisfaction of these requirements, the public entity owed a ministerial duty to issue final payment.  By providing the right to mandamus relief in the Act, the legislature intended to eliminate the public entity’s discretion to withhold payment from a contractor.

Suffolk Constr. Co. v. Rodriguez & Quiroga Architects Chtd., 2018 U.S. Dist. LEXIS 42652 (S.D. Fla. Mar. 15, 2018)

This case arises out of the design and construction of a science museum in Miami, Florida (the “Project”).  Museum of Science, Inc. (“MSI”), the Project owner, executed several agreements relating to the Project, including: (i) an agreement with Defendant Rodriguez and Quiroga Architects Chartered (“R&Q”) to serve as executive architect; (ii) an agreement with Defendant Grimshaw Architects P.C. (“Grimshaw”) to serve as the design architect; (iii) a construction services contract with Plaintiff Suffolk Construction Co. (“Suffolk”); and (iv) a direct contract with Suffolk’s subcontractor, Plaintiff Baker Concrete Construction, Inc. (“Baker”) for construction services after MSI terminated Suffolk for convenience.  After execution of these agreements, R&Q executed contracts with Defendant Fraga Engineers, LLC (“Fraga”) for mechanical, electrical, and plumbing design services, and with Defendant DDA Engineers, P.A. (“DDA”) for structural design and engineering services.

Suffolk and Baker (collectively, “Plaintiffs”) filed suit for negligence against R&Q, Grimshaw, Fraga, and DDA (collectively, “Defendants”), claiming that by issuing deficient design documents, Defendants breached their duties owed to Plaintiffs causing Plaintiffs to incur economic losses.  All Defendants but R&Q moved to dismiss the claims, arguing that they had no supervisory role or control over Plaintiffs, as demonstrated by the fact that their contracts with MSI did not designate them as “supervisory architects,” and thus, owed no duty to Plaintiffs.

Dormitory Auth. of the State of NY v. Samson Constr. Co., 2018 N.Y. Lexis 218 (February 15, 2018)

The Dormitory Authority of the State of New York (“DASNY”) undertook, as project manager, to construct a facility for the Office of the Chief Medical Examiner of the City of New York (the “City”) as a forensic biology laboratory (the “Project”).  DASNY retained Perkins Eastman Architects, P.C. (“Perkins”) as architect for the Project, and Samson Construction Co. (“Samson”) as the foundation contractor.

Complications during the construction of the foundation resulted in 18 months of delays due to the adjacent building settling eight inches, damages to the adjacent sidewalks, utilities and emergency repairs.  DASNY and the City filed suit against Samson, and later joined Perkins, asserting claims against Perkins for breach of contract and negligence.

Perkins moved for summary judgment to dismiss the City’s claims, and to dismiss DASNY’s negligence claim as duplicative of its breach of contract claim.  The trial court dismissed the City’s breach of contract claim; holding that the City was not an intended third-party beneficiary of the contract between DASNY and Perkins (the “Contract”), and allowed both DASNY’s breach of contract and negligence claims to proceed, holding that the claims were not duplicative of each another.

Cont’l Res. v. P&P Indus., LLC, 2018 N.D. Lexis 20 (January 22, 2018)

In 2013, Continental Resources Inc. (“Continental”), an oil producer doing business in North Dakota, entered into a master servicing agreement, governed by Oklahoma law, with United Oilfield Services (“United”).  According to the contract, United agreed to provide transportation, water hauling, and related support services to Continental in support of Continental’s ongoing operations in North Dakota.  The contract also contained the following termination provision: “[I]t being understood and agreed that either party hereto may cancel this Contract by giving the other party thirty (30) days written notice of such cancellation.”

Approximately a year after the parties signed the contract, Continental alleged that United (i) violated state and federal limits and regulations regarding the number of hours a truck driver may drive, (ii) violated Continental’s policy limiting the number of hours an employee could work in a day, and (iii) engaged in improper and fraudulent billing.  Following its discovery of United’s alleged misconduct, Continental terminated its contract and filed suit against United and other related entities.

Strickland v. Arch Ins. Co., No. 17-10610, 2018 U.S. App. LEXIS 504 (11th Cir. Jan. 9, 2018)

Strickland provided sand to a paving company (“Douglas”) for a Georgia Department of Transportation (“GDOT”) road improvement project (the “Project”).  Arch Insurance Company (“Arch”) issued payment and performance bonds on Douglas’s behalf.  In 2007, GDOT declared Douglas in default and removed it from the Project.  In accordance with the performance bond, Arch arranged for a third-party contractor to complete Douglas’s work on the Project. Strickland did not supply sand after Douglas’s removal.
In August 2010, GDOT determined that the Project was substantially complete, and in September 2010, performed final inspection and generated a punch list.  Arch’s contractor completed the punch list by September 2011.  In March 2012, GDOT accepted Project maintenance responsibilities because the Project had been satisfactorily completed as of September 2011.  GDOT made semi-final payment to Arch in July 2012.

In September 2012, Strickland sent a demand for payment on Arch’s payment bond.  Arch acknowledged the claim and asked for additional documentation.  Strickland did not respond.  In 2014, Strickland learned that GDOT was preparing to close out the Project and filed a lawsuit against Arch.

Lathan Co. v. State, No. 2016-CA-0913, 2017 La. App. LEXIS 2277 (La. App. 1st Cir. Dec. 6, 2017)

 
On December 6, 2017, the Louisiana Court of Appeals, First Circuit, reversed and remanded the trial court’s decision to grant the appellee’s, Jacobs Project Management Co./CRSS Consortium (“Jacobs”), motion for summary judgment.  In its opinion, the court of appeals held that a project manager owed a general contractor a duty of professional care and thus, could be held liable to a general contractor under Louisiana law, even if the project manager was not in direct privity with the general contractor.

On August 13, 2010, the appellant, The Lathan Company, Inc. (“Lathan”), entered into a public works contract with the State of Louisiana, Department of Education, Recovery School District (“Owner”) to renovate the William Frantz School in New Orleans.  Jacobs, through its contract with the Owner, served as project manager on behalf of the Owner.  Four years later, in August 2014, after filing an original lawsuit against the Owner in 2012 for payment of undisputed amounts due, Lathan filed an amended pleading that alleged inter alia Lathan was entitled to damages from Jacobs under general tort law for negligent professional undertaking and under Louisiana’s Unfair Trade Practices Act.  According to Lathan, Jacobs owed Lathan a duty of conduct in accordance with a standard of care similar to professionals in the industry and that Jacobs breached its duty of care by failing to (i) disclose mold conditions and the existence of an underground fuel tank at the outset of the project; (ii) timely respond to Lathan’s 400+ requests for information; (iii) perform inspections consistent with industry standards; and (iv) review, certify, and/or approve amounts due to Lathan.

S. Indus. Contractors, LLC v. Neel-Schaffer, Inc., No. 1:17CV255-LG-JCG, 2017 U.S. Dist. LEXIS 196804 (S.D. Miss. Nov. 30, 2017)

This case arises out of the West Pier Facilities project at the Port of Gulfport, Mississippi (“Project”).  Southern Industrial Contractors, LLC (“SIC”), the Project’s general contractor, filed suit for negligence against CH2M, the Project’s program manager and consultant, to recover increased costs incurred while excavating and working around underground debris at the Project site.  SIC alleged first that CH2M owed it a duty to ensure that the Project plans, specifications and bidding documents accurately represented the Project’s conditions, and second that CH2M breached this duty by failing to warn SIC of the underground obstructions it had encountered.  SIC argued that, as a result of CH2M’s breach, the Project became much more expensive and time-consuming.  CH2M filed a motion to dismiss the complaint, arguing it owed no duty to SIC.

The court first recognized that Mississippi law imposes upon design professionals, such as architects and engineers, a duty to exercise ordinary skill and diligence, and further, that Mississippi law allows third parties to rely upon the contractual obligations that a design professional owes to a project’s owner.  The court explained that, because of the design professional’s contractual obligations to the owner, the design professional owes a further duty, sounding in tort, to a contractor who relies upon the design to his economic detriment.  The court recognized that whether the design professional owes such a duty to a contractor is a factual determination that must be made on a case-by-case basis.

Tomlinson v. Douglas Knight Constr., Inc., 2017 Utah Lexis 132 (August 29, 2017)

This case arises out of the construction of a residential property.  Lot 84 Deer Crossing (“Lot 84”) purchased the property and contracted with Douglas Knight Construction, Inc. (“DKC”) to build a house on it.  The parties’ contract included a one-year construction warranty.  Lot 84 then assigned to Outpost Development, Inc. (“Outpost”) all of its rights in the property and the construction agreement.  As the home neared completion, Outpost noticed defects in its construction and, pursuant to the warranty, directed DKC to fix the deficiencies.  Despite DKC’s efforts, the defects remained.  Outpost then sold the home to Joseph Tomlinson, but did not assign to Tomlinson its interests in the DKC construction agreement.  Tomlinson subsequently noticed defects in the home and filed suit against Outpost and DKC.
Shortly thereafter, Outpost declared bankruptcy and was dismissed from the case.  During the bankruptcy proceedings, Tomlinson was assigned an interest in any claims that Outpost had asserted or may assert against DKC.  Tomlinson maintained that this assignment encompassed claims for breach of the DKC construction agreement and amended his complaint to include claims for breach of express and implied warranties.  Tomlinson sought to assert these claims as an assignee of rights of parties in privity with DKC: first, through the assignment made when Outpost purchased the property from Lot 84, and second, through the assignment in Outpost’s bankruptcy proceedings.  The district court rejected these theories and dismissed Tomlinson’s claims, holding that they were barred because Tomlinson had never acquired a direct interest in the DKC construction agreement.

WTE-S&S AG Enters., LLC v. GHD, Inc., 2017 Bankr. LEXIS 2343 (Bankr. N. D. Ill. August 18, 2017) 

This breach of contract dispute arises out of a contract to design and build a cow-manure digester on a farm in Wisconsin.  The digester vessel designed and constructed by Defendant, DVO, Inc. (formerly known as GHD, Inc.), consisted of a 300-foot long tank with two side-by-side chambers which were each 35 feet wide.  A thick concrete cover sat atop the vessel to prevent “free oxygen” from entering the digester.  A center wall ran the length of the vessel, separating the two chambers and also serving as the interior load-bearing wall.

The Debtor/owner commenced this action against DVO, contending, among other things, that the interior center wall footing of the vessel was defectively designed in that it was undersized and not compliant with the applicable code for waste-storage facilities.  Debtor’s expert testified that the undersized and overstressed wall footings could lead to settlement of the vessel and cracks in the foundation, which would compromise its structural integrity.  Debtor’s expert further testified that to properly support the vessel weight, the currently constructed three-foot wall footing needed to be three-and-a-half to four foot wide.

The court agreed that DVO’s design was defective and constituted a breach of the contract because it failed to comply with the applicable code.  However, applying the “economic waste” doctrine, the court denied Debtor’s request for damages of $988,475 to replace the entire vessel or, in the alternative, $655,000 to shut down and clean out the vessel to check for cracks or settlement issues.