Cresci Constr. Servs., Inc. v. Martin
2013 Pa. Super. LEXIS 154 (Pa. Super. Ct. Mar. 28, 2013)

Martin hired Cresci to build a home in exchange for $184,730. The Contract included a liquidated damages clause that applied if Martin canceled the contract before Cresci began constructing the home. The Contract did not include any other liquidated damage clauses.

Martin K. Eby Constr. Co., Inc. v. OneBeacon Ins. Co.,  
2012 U.S. Dist. LEXIS 131875 (D. Kan. Sept. 17, 2012)

Eby was the contractor for a project to build a water pipeline in Texas. KBR was the construction manager on the project. In the Indemnity Provision of the water pipeline project contract:

Eby agree[d] to indemnify and hold harmless KBR from and against any damages, claims, demands, suits, and judgment costs including attorney’s fees and expenses for or on account of damage to property directly or indirectly arising from or caused in connection with the work by Eby.”

Celanese, the owner of a methanol pipeline in the area near the project, sued Eby and KBR for negligence after the methanol pipeline leaked during the construction of the water pipeline. A jury determined that KBR was not liable to Celanese and that Eby’s actions caused the damage. But, KBR incurred attorney’s fees defending against the suit and sought to recover those fees from Eby under the Indemnity Provision.

First Gen. Constr. Corp., Inc. v. Kasco Constr. Co., Inc.
2011 U.S. Dist. LEXIS 55349 (E.D. Pa. May 24, 2011)

Kasco was the general contractor for a shopping center expansion. Kasco subcontracted the concrete work to First General. The subcontract included a term requiring First General to submit, upon request, releases of liens, with its payment applications. The Contract also required written approval of extra work, timely written notice of claims within ten days of their occurrence, and the submission of written backup information.