ThermoCor, Inc. v. United States,
1996 U.S. Claims LEXIS 68 (Cl. Ct. 1996).
On October 16, 1989, the United States Army Corps of Engineers (“Corps”) awarded ThermoCor, Inc. (“ThermoCor”) a contract in the amount of $15,500,000 to excavate and treat soils contaminated with polychlorinated biphenyls (“PCB’s”) in Erie County, New York. In part, the contract provided for estimated quantities, from which ThermoCor submitted a unit price bid. The contract also provided a Variance in Estimated Quantity Clause (“VEQ”), which provided, in pertinent part:
If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. 48 C.F.R. [[section]] 52.212-11 (1989) (emphasis supplied).

Valley View Enterprises, Inc. v. United States,
35 Fed. Cl. 378 (1996).
On September 22,1992, the Department of the Army awarded plaintiff Valley View Enterprises, Inc. (“Valley View”) a contract to replace seventeen steam lines located at the United States Military Academy in West Point, New York in connection with

R.W. Dunteman Company v. The Village of Lombard,
1996 Ill. App. LEXIS 375.
R.W. Dunteman Co. (Dunteman), entered into a construction contract with the Village of Lombard (Village), including the terms that Dunteman would remove and replace some road-way within the Village. The contract provided two different rates potentially applicable

Electro Assocs., Inc. v. Harrop Constr. Co., Inc.,
908 S.W.2d 21 1995 Tex. App. LEXIS 1968 (Tex. Ct. App. August 24, 1995).
Because the contractor-subcontractor relationship is not a “special relationship” giving rise to common law duty to act in good faith, subcontractor’s suit against general contractor for breach of

Grange Mutual Casualty Co. v. Robert Locker Builder, Inc.; Panzica Constr. Co. v. Ohio Ins. Casualty
1996 Ky. App. LEXIS 8 (Ky. Ct. App., Jan. 19, 1996); 1996 Ohio App. LEXIS 1975 (Ohio Ct. App., May 1
Provision in the standard broad form endorsement to comprehensive general liability insurance policy,

Kit-San-Azusa v. United States,
1996 U.S. App. LEXIS 10370 (Fed. Cir. Ct. App., May 7, 1996).
Government contractor’s differing site conditions claim based on the discovery of unanticipated boulders during excavation was upheld even though the Government’s general description of the site stated that cobbles and boulders were present at

Roy A. Elam Masonry, Inc. v. Fru-Con Construction Corporation,
1996 Mo. App. LEXIS 481 (March 26, 1996).
On November 14, 1988, the general contractor, Fru-Con Construction Corp. (Fru-Con) entered into a construction contract with Southwestern Redevelopment Corp (SRC), the owner. In early 1989, Fru-Con and a subcontractor Roy A. Elam

State of Florida, Department of Insurance v. The United States,
81 F.3d 1093 (U.S. App. 1996) LEXIS (Fed. Cir. 1996).
The construction contract at issue in this case resulted in a default termination of the contractor and the contractor’s surety. The surety’s receiver sued the United States for damages based

Hazleton Area School District v. Bosak,
671 A.2d 277 (Pa. Cmwlth. 1996).
In this case, neither of the arbitration provisions provided in the 1988 and 1989 agreements specifically stated that an action in tort for negligence should be arbitrated. The Commonwealth Court affirmed the decision of the trial court and