April 2023

Fed. Eng’rs & Constructors Inc. v. Relyant Global LLC, No. 3:19-CV-73-KAC-JEM, 2022 U.S. Dist. LEXIS 95617 (E.D. Tenn., May 27, 2022)

This case arises out of the renovation of a U.S. Air Force dormitory in Missouri. The U.S. Army Corps of Engineers hired Relyant Global LLC to act as the prime contractor. Relyant subcontracted with Federal Engineers and Constructors, Inc. (FE&C). Relyant later terminated its subcontract with FE&C. FE&C filed suit against Relyant, and Relyant moved for judgment on the pleadings.

Entech Engineering, P.C. v. Dewberry Engineers, Inc., 204 A.D.3d 467, 167 N.Y.S.3d 55 (1st Dep’t 2022)

The New York Supreme Court Appellate Division recently affirmed a ruling enforcing a pay-if-paid provision.

Defendant Dewberry Engineers, Inc. (Dewberry) contracted with the New York City Economic Development Corporations’ Build-It- Back Hurricane Sandy Program to inspect homes for structural, asbestos, and lead paint issues. Dewberry retained Entech Engineering PC (Entech) to perform pre-construction lead paint inspections of homes. The subcontract contained a pay-if-paid clause that made the city’s payment to Dewberry a condition precedent to Dewberry’s obligation to pay Entech.