February 2018

McMillin Albany LLC v. Superior Court, No. S229762, 2018 Cal. LEXIS 211 (Jan. 18, 2018)

Several homeowners (“Plaintiffs”) brought suit against developer/general contractor McMillin Albany LLC (“McMillin”) for alleged defective construction of new homes.  Plaintiffs alleged the defects caused property damage and economic loss in the form of repair costs and reduced property values, and asserted common law claims for negligence, strict product liability, breach of contract, and breach of warranty, and a statutory claim for violation of the construction standards outlined in the Right to Repair Act (Civ. Code §§ 895–945.5, the “Act”).  The Act defines standards for the construction of individual dwellings; governs various builder obligations, including provision of warranties; creates a prelitigation dispute resolution process; and describes mandatory procedures for lawsuits under the Act.  McMillin sought a stay of proceedings so that the parties could proceed through the Act’s prelitigation dispute process, which includes notice to the builder of defects and an opportunity to cure.  Plaintiffs refused to stipulate to the stay and instead, dismissed their statutory claim.  McMillin then sought a court-ordered stay which Plaintiffs contested, arguing that their suit now omitted any claim under the Act, and therefore, was not subject to its procedures.

United States ex rel. Metro Mech., Inc. v. Triangle Constr. Co.,  2018 U.S. Dist. LEXIS 1487 (S.D. Miss. Jan. 4, 2018)

Triangle Construction Company, Inc. (“Triangle”) contracted with Mississippi Portfolio Partners III, LP (“Mississippi Partners”) to serve as the prime contractor on four apartment complex construction projects (the “Projects”) in Mississippi.  Triangle subcontracted the HVAC and plumbing work to Metro Mechanical, Inc. (“Metro”).  After Metro completed its work, Metro filed suit in the Federal District Court under the Miller Act, to collect sums due from Triangle and its payment bond surety.  Triangle moved to dismiss, asserting that the Court was without Miller Act jurisdiction because the projects and contracting parties were private.

The Miller Act requires contractors on “public work[s] of the Federal Government” to obtain payment bonds for the protection of subcontractors and suppliers.  See 40 U.S.C. § 3131.  To that end, the Millers Act also creates a civil action in federal court in favor of any “person that has furnished labor or material in carrying out work provided for” under a Miller Act contract and “that has not paid in full within 90 days.” 40 U.S.C. 3133(b)(1).  The District Court applied two alternative tests to determine whether the Projects were “public works of the Federal Government subject to the Miller Act.”

Koudela v. Johnson & Johnson Custom Builders, LLC, 2017 Ohio App. Lexis 5800 (December 29, 2017)

In this case, Nicolas and Monica Koudela (the “Koudelas”) entered into a construction contract with “Johnson & Johnson Builders” (the “Agreement”), whereby Johnson & Johnson Builders agreed to construct a single family home for the Koudelas in Ohio.  However, Johnson & Johnson Builders was a fictitious name for Johnson & Johnson Custom Builders, LLC (“J&J”), and was not an entity registered with the Ohio Secretary of State.

In the Agreement, the parties agreed to submit all disputes to binding arbitration in Cleveland, Ohio.  The arbitration clause further provided that the cost of the arbitration would be borne by the party initiating the claim.

After disputes arose on the project regarding the work performed by J&J, the Koudelas filed suit in the State Court of Ohio against J&J and its principals, alleging claims for fraud in the inducement, breach of contract, negligence, conversion, unjust enrichment/detrimental reliance, and a declaratory judgment that the arbitration clause in the Agreement was unenforceable.  J&J moved for an order dismissing the complaint, or, in the alternative, staying the litigation pending binding arbitration.  The trial court granted J&J’s motion and stayed the litigation pending binding arbitration.

Addison Ins. Co. v. 4000 Island Blvd. Condo. Ass’n, 2017 U.S. App. LEXIS 26870 (11th Cir. Dec. 28, 2017)

The owner of a high-rise condominium building in Florida hired a contractor to replace the building’s concrete balcony railings with new railings featuring aluminum and glass.  The contractor on the project, Poma Construction (“Poma”), entered into a subcontract with Windsor Metal Specialties (“Windsor”), under which Windsor agreed to paint the new aluminum railings.

Two years after the work was completed, the owner sued Poma and Windsor in Florida state court, alleging that the railings were defective and required replacement.  In addition to replacing the railing system, the owner alleged that Windsor’s defective paint finish damaged other surrounding property, including railing post pockets and the concrete balcony slabs.

Windsor submitted the claim to its liability carrier, Addison Insurance Company (“Addison”).  Addison then filed a declaratory judgment action in the United States District Court for the Southern District of Florida, seeking a declaration that it had no duty to defend Windsor in the owner’s underlying lawsuit.  Windsor’s policy provided a defense against claims alleging that an “occurrence” caused “property damage.”  But the policy excluded claims alleging damage to Windsor’s own work product or to the particular part of a property on which Windsor performed its work.  Addison had invoked that exclusion, arguing that the owner merely alleged damage to Windsor’s own work and/or the part of the property on which Windsor performed its work, i.e. the balcony.  The District Court granted summary judgment in favor of Windsor, and Addison appealed.