Zirkelbach Constr., Inc. v. DOWL, LLC, 2017 Mont. Lexis 591 (Mont., Sept. 26, 2017)
In interpreting a state statute which makes contractual limitations on a party’s liability unenforceable in certain instances, the Supreme Court of Montana recently upheld the validity of a contract provision in a professional services agreement between a general contractor and a designer in which the parties waived consequential damages against each other and limited the liability of the designer to $50,000.00.
Zirkelbach Constr., Inc. (“Zirkelbach”) and DOWL, LLC (“DOWL”) entered into a professional services agreement (the “Agreement”), whereby DOWL agreed to provide design work to Zirkelbach, a general contractor, for the construction of a FedEx Ground facility in Billings, Montana. The original contract price was $122,967, but was adjusted to approximately $665,000 after the parties made several addenda to the Agreement to account for additional services.Continue Reading Montana Supreme Court Holds That a Waiver of Consequential Damages and a Partial Limitation of Liability in a Design Contract Are Not Contrary to Montana Law