Shelter Prods. v. Steelwood Constr., Inc.
307 P.3d 449 (Or. Ct. App. 2013)

This action arose from a payment dispute between a general contractor, Catamount Constructors, Inc. (“Catamount”), and one of its subcontractors, Steelwood Construction, Inc. (“Steelwood”). Catamount contracted with Steelwood (the “Subcontract”) to provide materials and perform work for the construction of a Home Depot distribution center in Salem, Oregon (the “Project”). Included in the Subcontract was a provision that allowed Catamount to terminate the Subcontract for convenience and “without cause.” In the event the Subcontract was terminated for convenience, Steelwood would be entitled to the cost of all work performed on the Project as of the date of termination.


Continue Reading Oregon Court of Appeals Holds General Contractor Cannot Offset Costs of Repairing Subcontractor’s Defective Work After Subcontractor Is Terminated “For Convenience” Without an Opportunity to Cure