Structure Tone, Inc. v. Universal Services Group, Ltd.
929 N.Y.S. 2d 242 (App. Div. 2011)

This action arose out of the construction of a Whole Foods Market in the AOL/Time Warner Center at Columbus Circle in Manhattan. The general contractor, Structure Tone, Inc., (“STI”) retained Universal Service Group (“USG”) to waterproof the market. STI sued USG, claiming that the waterproofing failed on 15 occasions, causing water to leak from the Whole Foods Market into various tenant spaces below. STI undertook to remedy the problem, and as a result, allegedly sustained damages totaling $1.2 million. STI alleged causes of action for negligence and breach of contract, seeking as damages the costs of remediation, loss of profit, recovery of the amounts paid to USG and contract balances not paid by Whole Foods.