United States ex rel. Tymatt Indus. v. Allen & Shariff Constr. Servs.
2013 U.S. Dist. LEXIS 114015 (D. Md. Aug. 13, 2013)

This action arose out of a subcontractor’s Miller Act claim for unpaid contract balances on a federal construction project. Allen & Shariff Construction Services, LLC (“Allen & Shariff”) was the prime contractor on a federal contract for the construction of a dam in Bethesda, Maryland, and related remediation (the “Project”). United States Security Company (“USSC”) was the surety on the Miller Act payment bond for the Project. Allen & Shariff subcontracted with Tymatt Industries, Inc. (“Tymatt”) to perform work on the Project (the “Subcontract”). The Subcontract contained a default provision stating that “should Tymatt fail to perform, after giving three days written notice Allen & Shariff had the option to terminate the [S]ubcontract for default if the defective performance was not cured.” Allen & Shariff issued three such notices to Tymatt, the last of which was issued on November 11, 2011. When Tymatt failed to cure, USSC sent Tymatt a termination notice on November 18, 2011 stating that the “[S]ubcontract…has been terminated due to lack of performance effective immediately.” Additionally, Allen & Shariff notified Tymatt that its “base access privilege [would] be terminated on November 23, 2011,” and requested that its equipment be removed prior to that date. Tymatt subsequently alleged that Allen & Shariff failed to pay $107,665.26 in amounts owed for work performed under the Subcontract. On Monday, November 26, 2012, Tymatt filed a Miller Act claim against USSC, as surety, to recover the monies allegedly due and owing.