Razorback Contractors Inc. v. Board of County Commissioners

Razorback Contractors Inc. v. Board of County Commissioners
227 P.3d 29 2010 Kan. App. LEXIS 35 (Kan. Ct. App. April 2, 2010)

The Court of Appeals of Kansas recently upheld a trial court’s decision to strictly enforce a written notification of differing site conditions provision in a construction contract.

The matter before the Court of Appeals involved construction of a sanitary sewer line in Southern Johnson County, Kansas. Defendant the Johnson County Board of County Commissioners contracted Plaintiff Razorback Contractors of Kansas, Inc., the successful bidder on the Project, to provide construction services in connection with the Project.Continue Reading Kansas Court Strictly Construes Written Notification of Differing Site Conditions Clause