Aquatic Renovations Sys. v. Vill. of Walbridge, 2018 Ohio App. Lexis 1581 (April 13, 2018)

This post was published on July 7, 2018 in The Pennsylvania Record.

On May 2, 2012, Aquatic Renovations Systems, Inc. (“Aquatic”) entered into a contract with the Village of Walbridge (“the Village”) for the installation of a new pool liner (“Contract 1”).  Prior thereto, the Village council adopted an ordinance which authorized the mayor to enter into Contract 1 (“Ordinance”).  On April 12, 2013, the mayor signed a new contract for the balance of the work (“Contract 2”).  A few days after Aquatic completed its work, the pool liner began to lift.  The Village then refused to pay Aquatic for the completed and approved work.

Aquatic sued the Village for non-payment, alleging the Village breached Contract 2.  Aquatic also alleged that the Village was liable under a theory of quantum meruit and unjust enrichment.  The trial court granted the Village’s motion for summary judgment, holding that Contract 2 was not valid because it did not comply with the Ohio Revised Statute which required the mayor, the clerk, and the Village administrator to authorize all Village Contracts.  Thus, because Contract 2 was unenforceable, Aquatic could not recover under a breach of contract, quantum meruit or unjust enrichment theory.

Continue Reading Void Means Void – Municipal Contract That Did Not Conform to Statute Is Void and No Claim for Breach or Quasi-Contract or Unjust Enrichment Is Permitted

Archon Construction Co. v. U.S. Shelter, LLC, 2017 Ill. App. LEXIS 197 (March 31, 2017)

U.S. Shelter, LLC, a developer, undertook to develop a new residential subdivision in Elgin, Illinois. As part of that project, U.S. Shelter retained Archon Construction Company, Inc. (“Archon”) to install the sanitary sewer system for $890,955.29.

Archon’s contract provided that after the system was completed, Archon would videotape the interior of the piping, to allow the City of Elgin (“City”) to inspect and determine the acceptability of the system as installed.

Archon completed its work in August of 2005. In early 2007, the City requested that Archon perform the required videotaping.  Archon complied.

After viewing the videotapes, the City announced that the system, as installed, was not acceptable and that certain repairs were necessary. In particular, the City specified that one of the lines running through the system needed to be replaced because of cracking, the existence of gravel in the lines, and other issues.  While the entire sewer system had been constructed with PVC pipe, the City directed that this line be replaced with ductile iron pipe.

Continue Reading Illinois Appellate Court Attempts to Draw the Line Between Contract and Quasi-Contract; Holds That Quantum Meruit Is Only Available Where Disputed Work is Outside the “General Subject Matter” of the Contract

Northeast Fence & Iron Works, Inc. v. Murphy Quigley Co.
933 A.2d 664, 2007 Pa. Super. LEXIS 3092 (Pa. Super. Ct. Sept. 18, 2007)
The Pennsylvania Superior Court held that a subcontractor could recover on a theory of unjust enrichment against a contractor where the subcontractor proved that it performed work for which it was not paid and that this work satisfied the contractor’s obligations to a third party. The Subcontractor was not required to prove payment to the Contractor by the Owner.

Continue Reading Pennsylvania Superior Court Clarifies Criteria for Unjust Enrichment Recovery by Subcontractor