P.A.L. Environmental Safety Corp. v. North American Dismantling Corp. Et Al., No. 19-11630, 2020 BL 198779 (E.D. Mich. May 28, 2020)

A Michigan federal court partially granted Consumers Energy Company’s (“CEC”) motion to dismiss P.A.L. Environmental Safety Corporation’s (“PAL”) complaint alleging numerous causes of action in connection with its suit against CEC and contractor North American Dismantling Corporation (“NADC”) for outstanding payment stemming from asbestos abatement work at a CEC-owned power plant in Essexville, Michigan (the “Power Plant”).

According to the decision, CEC, as owner, and NADC, as prime contractor, entered into a written contract whereby NADC agreed to abate, dismantle, and demolish the Power Plant.  In turn, NADC subcontracted with PAL to perform abatement of all asbestos containing material at the Power Plant.  While the subcontract price was $7,996,331, PAL alleged entitlement to an adjusted price of $23,841,833 in unpaid labor and materials for its asbestos abatement work.  Specifically, PAL alleges that it performed additional work not accounted for in the subcontract including fly ash and coal dust removal, refractory brick abatement, and extra asbestos removal.

While PAL’s complaint included numerous counts against Defendants NADC, CEC, and labor and material payment bond surety North American Specialty Insurance Company (“NASIC”), the opinion is most notable for its treatment of CEC’s motion to dismiss several counts against it including: (i) quasi-contractual claims; (ii) a third-party breach of contract claim; and (iii) a negligent misrepresentation claim.

Skyrise Construction Group, LLC v. Annex Construction, LLC, 2019 BL 55071 (E.D. Wis. Feb. 20, 2019)

Subcontractor Skyrise Construction, Inc. (“Skyrise”) sued general contractor Annex Construction, Inc. (“Annex”) for breach of contract, promissory estoppel, negligent misrepresentation, and violations of Wisconsin and Illinois trade practices statutes.  Skyrise primarily based its claims on an assertion that the parties entered into a subcontract, which Annex breached when it removed Skyrise from the project and completed the work with an alternative subcontractor.  Both Skyrise and Annex filed motions for summary judgment.  The District Court denied Skyrise’s motion and granted Annex’s motion.

Hartford Fire Insurance Co. v. City of Mont Belvieu
2010 U.S. App. Lexis 14277 (5th Cir. July 13, 2010)

The Court of Appeals for the Fifth Circuit recently held that a Texas City’s bond claim was time barred under the statute of limitations and equitable remedies based on estoppel were unavailable to revive claims on the bond.

Hartford Fire Insurance Company issued a performance bond for a contractor constructing a public recreational facility for the City of Mont Belvieu, Texas. The bond was a requirement under Texas public work contracts. By statute, the bond was subject to a one-year limitations period commencing from project final completion. The project progressed with numerous delays and changes. However, the City issued a certificate of occupancy in mid-2001, taking possession and operating the facility by July 2002.

At that time, numerous punch list items remained and several subcontractors owed payment by contractor filed claims on a payment bond. Hartford advised the City to be cautious when releasing further payment to contractor. Thereafter, in July 2002, City paid contractor almost $675,000 as an equitable adjustment via a change order. Critically, the change order stated that the project’s completion date was July 19, 2001.

Lahr Construction Corp. (doing business as LeCesse Construction Co.) v. J. Kozel & Son, Inc.,
640 N.Y.S.2d 957 (Misc 1996).
This is an action brought by a general contractor against a subcontractor for damages where the subcontractor moved for summary judgment saying that the general contractor could not recover damages…