Arco Ingenierosm, S.A. v. CDM Int’l Inc., Civil Action No. 18-12348-PBS, 2019 BL 100779 (D. Mass. Mar. 22, 2019)

In November 2009, Tropical Storm Ida hit El Salvador, causing flooding, landslides, and the destruction of homes, roads, bridges, schools, health clinics, and other infrastructure.  The United States Agency for International Development (“USAID”) provided $25 million in funding to rebuild damaged infrastructure.  USAID retained Defendant CDM International Inc. (“CDM”) to conduct studies and assessment for the construction of eight schools and one health clinic (the “Projects”) and to create preliminary designs and technical specifications for these Projects.  These preliminary designs were intended to constitute at least thirty percent of final designs for the Projects.  Relying on the preliminary designs created by CDM, Plaintiff Arco Ingenieros, S.A. de C.V. (“ARCO”) submitted bids to act as the design-build contractor for the Projects.  USAID awarded the Projects to ARCO.