A.E. Rosen Elec. Co. v. Plank, LLC, No. 07862-7, 2019 BL 113951 (Sup. Ct. Mar. 01, 2019)

On March 1, 2019, the Supreme Court of New York, Albany County, granted a subcontractor’s motion for summary judgment on a payment dispute involving a “pay-when-paid” contract provision.

Defendant Plank, LLC (“Contractor”) entered into a construction contract with Dutch Village, LLC (“Owner”) to act as the general contractor for the construction of four apartment buildings (“Project”).  Thereafter, Contractor entered into a subcontract with Plaintiff A.E. Rosen Electrical, Inc. (“Subcontractor”) for electrical work on the Project.  After nine months of work on the Project, a payment dispute arose between the Owner and Contractor.  At that time, Contractor directed the Subcontractor to cease work on the Project.

Matter of Red Hook 160 LLC v. Borough Constr. Grp. LLC, No. 524909/18, 2019 BL 122210 (N.Y. Sup. Ct. Mar. 19, 2019)

This cases arises out of a project owner’s request for further itemization of amounts claimed in a construction manager’s mechanic’s lien.  Red Hook 160 LLC (“Red Hook”), the owner of the property sought to be liened, demanded a revised itemized statement of the mechanics’ lien filed by Borough Construction Group, LLC (“BCG”), the construction manager hired in connection with the construction and renovation of a six story building located at 160 Imlay Street in Kings County, New York.