Sloan & Co. v. Liberty Mutual Ins. Co.
633 F. 3d 175 (3d Cir. 2011)
IOC developed a waterfront condominium project in Philadelphia. Shoemaker was the prime contractor for the Project. Shoemaker retained multiple contractors, including Sloan, who was to perform drywall and carpentry work. Liberty Mutual was Shoemaker’s payment bond surety. At completion, IOC refused to pay Shoemaker nearly $6.5 million. Of that amount, $5 million was due to subcontractors. IOC claimed, among other things, that some of the subcontractors’ work was untimely and deficient. Because of this, Shoemaker refused to pay Sloan of the remaining balance due under its subcontract, $1,074,260.Continue Reading Third Circuit, Reversing District Court, Holds Subcontract Payment Clause Shifted Risk of Nonpayment by Owner to Subcontractor