Indianapolis – Marion County Public Library v. Charlier Clark & Linard, P.C
2010 Ind. LEXIS 397 (Indiana, June 29, 2010)

The Indianapolis-Marion County Public Library entered into contracts with Woollen Molzan and Partners, Inc. (“Architect”) for the design for the renovation and expansion of the Library’s facility including its parking garage. The Architect entered into subcontracts with Thornton Tomasetti Engineers (“TTE”) and Charlier Clark and Linard, P.C. (“CCL”) to perform architectural and engineering services. TTE performed structural engineering services and CCL administered various services for the Project, including reviewing and inspecting the construction plans and construction progress to determine if construction was in general compliance with the construction documents. The Library never consulted directly with TTE or CCL.

Hunt Construction Group, Inc. v. Brennan Beer Gorman / Architects, P.C.
2008 U.S. Dist. LEXIS 93754 (D. Vt. 2008)

In declining to apply an exception to the economic loss rule, the Court dismissed a contractor’s negligence claims against the project architect (and other design professionals).

In 2005, Spruce Peak Realty, LLC (“Owner”), retained Plaintiff, Hunt Construction Group (“Contractor”), to construct a resort hotel in Stowe, Vermont. Owner and Contractor executed a contract setting forth their respective rights and responsibilities on the Project. Owner then contracted with an architect, mechanical, electrical and plumbing engineers, a structural engineer, and an interior designer (collectively, the “Design Professional Defendants”). Contractor was to build the Project according to the plans and specifications the Design Professional Defendants provided under contracts with Owner.