A.E. Rosen Elec. Co. v. Plank, LLC, No. 07862-7, 2019 BL 113951 (Sup. Ct. Mar. 01, 2019)

On March 1, 2019, the Supreme Court of New York, Albany County, granted a subcontractor’s motion for summary judgment on a payment dispute involving a “pay-when-paid” contract provision.

Defendant Plank, LLC (“Contractor”) entered into a construction contract with Dutch Village, LLC (“Owner”) to act as the general contractor for the construction of four apartment buildings (“Project”).  Thereafter, Contractor entered into a subcontract with Plaintiff A.E. Rosen Electrical, Inc. (“Subcontractor”) for electrical work on the Project.  After nine months of work on the Project, a payment dispute arose between the Owner and Contractor.  At that time, Contractor directed the Subcontractor to cease work on the Project.