Neshaminy Constructors, Inc. v. Concrete Building Systems, Inc.
2007 U.S. Dist. LEXIS 69197, Civil Action No. 06-1489 (E.D. Pa. 2007)
The United States District Court for the Eastern District of Pennsylvania conducted a bench trial in which the primary question was whether a contract had been formed between a contractor and subcontractor in connection with a project for which the contractor submitted a bid proposal utilizing, in part, the subcontractor’s bid proposal for calculating the total price for the work. Relying on Pennsylvania common law, the Eastern District held that use of a subcontractor’s bid, by a general contractor in the submission of its own bid to the owner, in and of itself is not sufficient to create a binding contract.