Northeast Fence & Iron Works, Inc. v. Murphy Quigley Co.
933 A.2d 664, 2007 Pa. Super. LEXIS 3092 (Pa. Super. Ct. Sept. 18, 2007)
The Pennsylvania Superior Court held that a subcontractor could recover on a theory of unjust enrichment against a contractor where the subcontractor proved that it performed work for which it was not paid and that this work satisfied the contractor’s obligations to a third party. The Subcontractor was not required to prove payment to the Contractor by the Owner.