LLC v. Keating Building Corp. v. Roman Mosaic and Tile Co.

La Liberte, LLC v. Keating Building Corp. v. Roman Mosaic and Tile Co.
Civ. A. No. 07-1397, 2007 U.S. Dist. LEXIS 90878 (E.D. Pa., Dec. 11, 2007)
The United States District Court for the Eastern District of Pennsylvania dismissed the third-party complaint of the defendant holding that the statute of limitations had expired on the defendant’s performance bond claims against surety companies.
Plaintiff La Liberte LLC sued Defendant Keating Building Corporation for breach of contract, breach of implied warranty, and breach of express warranty in connection with the work Keating performed on a hotel owned by La Liberte. Under the contract between La Liberte and Keating, Keating was to make renovations and construct an addition to La Liberte’s hotel. Keating, in turn, entered into several subcontracts. Among them, Keating contracted with Voegele Mechanical Inc. and Shannon Plastering and Drywall Corporation. Both subcontracts contained warranty provisions which ran one year from acceptance by La Liberte. Voegele and Shannon obtained performance bonds for the benefit of Keating. The performance bonds contained the following identical provisions: