LBL Skysystems (USA), Inc. v. APG-America, Inc.
No. 02-5379, 2005 U.S. Dist. LEXIS 19065 (E.D.Pa. Aug. 31, 2005)
In LBL Skysystems (USA), Inc. v. APG-America, Inc., No. 02-5379, 2005 U.S. Dist. LEXIS 19065 (E.D.Pa. Aug. 31, 2005), the District Court concluded that a subcontractor was contractually obligated to continue performance, despite its dispute with the contractor over alleged extra work. Further, the Court concluded that the subcontractor was in the wrong, as its course of performance demonstrated that certain steel work was, in fact, within the subcontractor’s original work scope. As a result, the Court concluded that the contractor’s decision to terminate the subcontract was proper.
Continue Reading Flow Down Provision Requires Subcontractor to Proceed During Pendency of Dispute Over Extra Work – A Dispute The Subcontractor Loses as a Result of Course of Performance