L.P. v. Travelers Property Casualty Co. of American

Oceanside Pier View, L.P. v. Travelers Property Casualty Co. of American
2008 U.S. Dist. LEXIS 37755 (S.D. Cal. May 6, 2008)
The U.S. District Court for the Southern District of California considered whether the basic coverage of a $28 million Builders Risk policy applied to the increased cost to complete construction of the unbuilt portion of a mixed use project attributable to delays which resulted from the failure of a shoring wall during construction. The court held that the basic Builders Risk coverage did not apply, and that coverage for increased costs of completing structures which were not under construction at the time of failure was subject to the $100,000 limit of “additional coverage” provided for “Expediting Costs and Additional Cost of Construction Materials and Labor”.