Gables Construction, Inc. v. Red Coats, Inc., No. 23, 2020 BL 193791, 2020 MD LEXIS 264 (Md. May 26, 2020)

Upper Rock II, LLC (“Upper Rock”) contracted Gables Construction, Inc. (“GCI”) to construct a multi-building apartment complex in Rockville, Maryland (the “Project”) per the terms of the American Institute of Architects (“AIA”) A102TM-2007, Standard Form Agreement Between Owner and Contractor and AIA A201TM – 2007, General Conditions of the Contract for Construction.  The General Conditions required Upper Rock to purchase and maintain a property insurance policy.  It also contained a waiver of subrogation provision under which Upper Rock waived all rights against GCI and other Project participants for damages caused by fire to the extent covered by insurance.

Village of Sturtevant v. STS Consultants, Ltd.
2010 Wisc. App. LEXIS 433 (Wis. Ct. App. June 9, 2010)

The Court of Appeals of Wisconsin recently considered whether a design professional could maintain a claim for contribution against a subcontractor on the basis that the subcontractor had a duty to advise that the design was not suited for the intended application. The Court of Appeals upheld the lower court’s dismissal of such claims on the basis that the subcontractor had no design or construction responsibility and therefore could not be a joint tortfeasor.