DAK Americas Mississippi, Inc. v. Jedson Engineering, Inc. et al, No. 1:18cv31-HSO-JCG, 2019 BL 208838 (S.D. Miss. June 6, 2019)
This dispute arose out of the design and construction of a concrete storage slab at DAK’s polymer resin manufacturing facility located in Hancock County, Mississippi. DAK hired Ohio-based Jedson to design and oversee the construction of a cement slab suitable for commercial operating loaders and other heavy equipment necessary to transport, unload, and stack shipping containers. DAK allegedly discovered substantial cracking and chipping of the cement, and filed suit in federal court claiming Jedson failed to design a slab suitable for DAK’s intended purposes. DAK asserted claims for negligent design, negligent construction management, and breach of contract.
Continue Reading Federal Court Finds That Ambiguous Limitation-of-Liability Clause Did Not Clearly Restrict Owner’s Claims