A.E. Rosen Elec. Co. v. Plank, LLC, No. 07862-7, 2019 BL 113951 (Sup. Ct. Mar. 01, 2019)

On March 1, 2019, the Supreme Court of New York, Albany County, granted a subcontractor’s motion for summary judgment on a payment dispute involving a “pay-when-paid” contract provision.

Defendant Plank, LLC (“Contractor”) entered into a construction contract with Dutch Village, LLC (“Owner”) to act as the general contractor for the construction of four apartment buildings (“Project”).  Thereafter, Contractor entered into a subcontract with Plaintiff A.E. Rosen Electrical, Inc. (“Subcontractor”) for electrical work on the Project.  After nine months of work on the Project, a payment dispute arose between the Owner and Contractor.  At that time, Contractor directed the Subcontractor to cease work on the Project.

SMJ Gen. Constr., Inc. v. Jet Commer. Constr., LLC, No. S-16785/16985, 2019 BL 131640 (Alaska Apr. 12, 2019)

In 2016, Jet Commercial Construction, LLC (“Jet”) entered into a subcontract with SMJ General Construction, Inc. (“SMJ”) to supply materials and labor for the construction of a restaurant in Hawaii.  The subcontract contained a dispute resolution provision that required the parties to first mediate any dispute and then submit it to arbitration if mediation was unsuccessful.  It also included a choice-of-law and venue provision designating Oklahoma Law and the courts of Cleveland County, Oklahoma for any lawsuits pertaining to the Agreement’s enforcement.